Westport Workshop Concrete Pad & Drainage Upgrade
Client-Ready Starter Schedule Pack
Specimen Client Submission PackThis example shows the report and schedule pack produced from the completed specimen workbook.
Download Complete ZIP Pack
Download Professional PDF
Download Microsoft Project XML
Use the Schedule Builder
Microsoft Project XML opens in Microsoft Project and can then be saved as an .mpp file. P6 XER export will be added only after native P6 validation.
21 Oct 2026Calculated Finish
23-Oct-2026Contract Date
2 working days earlyCompletion Position
16Critical Activities
9Peak People
149Planned People-Days
Executive schedule position
The logic-linked programme forecasts completion on 21 Oct 2026, which is 2 working days early against the stated contract completion date. The workforce reaches a planned peak of 9 people in the week of 28 sep 2026.
Logic-Linked Gantt Programme
Every date below is calculated from the entered durations, relationships, work week and calendar exceptions.
Critical PathNon-Critical Work
Activity
07 Sep16 Sep25 Sep05 Oct14 Oct23 Oct
A1000 Contract Award and Notice to Proceed
Project Management / Contract Milestones · 07 Sep 2026 to 07 Sep 2026 · 0 people
Project Management / Contract Milestones · 07 Sep 2026 to 07 Sep 2026 · 0 people
A1010 Kick-off meeting and confirm client requirements
Project Management / Planning & Approvals · 08 Sep 2026 to 09 Sep 2026 · 2.0 people
Project Management / Planning & Approvals · 08 Sep 2026 to 09 Sep 2026 · 2.0 people
A1020 Site measure, survey and service locating
Project Management / Planning & Approvals · 10 Sep 2026 to 11 Sep 2026 · 3.0 people
Project Management / Planning & Approvals · 10 Sep 2026 to 11 Sep 2026 · 3.0 people
A1030 Submit SWMS, ITP and construction details
Project Management / Planning & Approvals · 10 Sep 2026 to 12 Sep 2026 · 1.0 people
Project Management / Planning & Approvals · 10 Sep 2026 to 12 Sep 2026 · 1.0 people
A1040 Client approval to commence site works
Project Management / Contract Milestones · 14 Sep 2026 to 14 Sep 2026 · 0 people
Project Management / Contract Milestones · 14 Sep 2026 to 14 Sep 2026 · 0 people
A1050 Procure drainage pits and pipework
Procurement / Drainage Materials · 15 Sep 2026 to 22 Sep 2026 · 1.0 people
Procurement / Drainage Materials · 15 Sep 2026 to 22 Sep 2026 · 1.0 people
A1060 Procure reinforcement, formwork and embeds
Procurement / Concrete Materials · 15 Sep 2026 to 19 Sep 2026 · 1.0 people
Procurement / Concrete Materials · 15 Sep 2026 to 19 Sep 2026 · 1.0 people
A1070 Mobilise and establish site
Construction / Mobilisation · 15 Sep 2026 to 16 Sep 2026 · 3.0 people
Construction / Mobilisation · 15 Sep 2026 to 16 Sep 2026 · 3.0 people
A1080 Set out works and isolate construction area
Construction / Mobilisation · 17 Sep 2026 to 17 Sep 2026 · 2.0 people
Construction / Mobilisation · 17 Sep 2026 to 17 Sep 2026 · 2.0 people
A1090 Saw cut and demolish existing pavement
Construction / Demolition & Earthworks · 18 Sep 2026 to 21 Sep 2026 · 4.0 people
Construction / Demolition & Earthworks · 18 Sep 2026 to 21 Sep 2026 · 4.0 people
A1100 Excavate drainage trench and slab box
Construction / Demolition & Earthworks · 22 Sep 2026 to 25 Sep 2026 · 5.0 people
Construction / Demolition & Earthworks · 22 Sep 2026 to 25 Sep 2026 · 5.0 people
A1110 Install drainage pipework and pits
Construction / Drainage · 26 Sep 2026 to 29 Sep 2026 · 4.0 people
Construction / Drainage · 26 Sep 2026 to 29 Sep 2026 · 4.0 people
A1120 Prepare subgrade and compact basecourse
Construction / Concrete Works · 26 Sep 2026 to 28 Sep 2026 · 4.0 people
Construction / Concrete Works · 26 Sep 2026 to 28 Sep 2026 · 4.0 people
A1130 Install formwork, reinforcement and embeds
Construction / Concrete Works · 29 Sep 2026 to 02 Oct 2026 · 5.0 people
Construction / Concrete Works · 29 Sep 2026 to 02 Oct 2026 · 5.0 people
A1140 Client pre-pour inspection accepted
Project Management / Contract Milestones · 03 Oct 2026 to 03 Oct 2026 · 0 people
Project Management / Contract Milestones · 03 Oct 2026 to 03 Oct 2026 · 0 people
A1150 Place, finish and test concrete
Construction / Concrete Works · 06 Oct 2026 to 07 Oct 2026 · 8.0 people
Construction / Concrete Works · 06 Oct 2026 to 07 Oct 2026 · 8.0 people
A1160 Concrete curing and protection
Construction / Concrete Works · 08 Oct 2026 to 13 Oct 2026 · 2.0 people
Construction / Concrete Works · 08 Oct 2026 to 13 Oct 2026 · 2.0 people
A1170 Strip formwork, reinstate surrounds and clean site
Completion / Reinstatement · 14 Oct 2026 to 16 Oct 2026 · 4.0 people
Completion / Reinstatement · 14 Oct 2026 to 16 Oct 2026 · 4.0 people
A1180 Complete testing, as-builts and handover inspection
Completion / Handover · 17 Oct 2026 to 20 Oct 2026 · 2.0 people
Completion / Handover · 17 Oct 2026 to 20 Oct 2026 · 2.0 people
A1190 Practical Completion
Completion / Contract Milestones · 21 Oct 2026 to 21 Oct 2026 · 0 people
Completion / Contract Milestones · 21 Oct 2026 to 21 Oct 2026 · 0 people
Workforce and Planned Progress
Weekly Manning Profile
Average planned people per working day. No trade or crew breakdown is assumed.
Planned Progress Curve
Progress is weighted by People Required × task duration.
Weekly Planned ProgressCumulative Planned Progress
Milestone Register
| Milestone | Forecast | Required | Variance | Position |
|---|---|---|---|---|
| A1000 Contract Award and Notice to Proceed | 07 Sep 2026 | Not set | — | No required date |
| A1040 Client approval to commence site works | 14 Sep 2026 | 15 Sep 2026 | -1 working days | On or before requirement |
| A1140 Client pre-pour inspection accepted | 03 Oct 2026 | 09 Oct 2026 | -4 working days | On or before requirement |
| A1190 Practical Completion | 21 Oct 2026 | 23 Oct 2026 | -2 working days | On or before requirement |
Calculated Critical Path
| ID | Critical Activity | Start | Finish | Duration | People |
|---|---|---|---|---|---|
| A1000 | Contract Award and Notice to Proceed | 07 Sep 2026 | 07 Sep 2026 | 0 workdays | 0 |
| A1010 | Kick-off meeting and confirm client requirements | 08 Sep 2026 | 09 Sep 2026 | 2 workdays | 2.0 |
| A1030 | Submit SWMS, ITP and construction details | 10 Sep 2026 | 12 Sep 2026 | 3 workdays | 1.0 |
| A1040 | Client approval to commence site works | 14 Sep 2026 | 14 Sep 2026 | 0 workdays | 0 |
| A1070 | Mobilise and establish site | 15 Sep 2026 | 16 Sep 2026 | 2 workdays | 3.0 |
| A1080 | Set out works and isolate construction area | 17 Sep 2026 | 17 Sep 2026 | 1 workdays | 2.0 |
| A1090 | Saw cut and demolish existing pavement | 18 Sep 2026 | 21 Sep 2026 | 3 workdays | 4.0 |
| A1100 | Excavate drainage trench and slab box | 22 Sep 2026 | 25 Sep 2026 | 4 workdays | 5.0 |
| A1120 | Prepare subgrade and compact basecourse | 26 Sep 2026 | 28 Sep 2026 | 2 workdays | 4.0 |
| A1130 | Install formwork, reinforcement and embeds | 29 Sep 2026 | 02 Oct 2026 | 4 workdays | 5.0 |
| A1140 | Client pre-pour inspection accepted | 03 Oct 2026 | 03 Oct 2026 | 0 workdays | 0 |
| A1150 | Place, finish and test concrete | 06 Oct 2026 | 07 Oct 2026 | 2 workdays | 8.0 |
| A1160 | Concrete curing and protection | 08 Oct 2026 | 13 Oct 2026 | 5 workdays | 2.0 |
| A1170 | Strip formwork, reinstate surrounds and clean site | 14 Oct 2026 | 16 Oct 2026 | 3 workdays | 4.0 |
| A1180 | Complete testing, as-builts and handover inspection | 17 Oct 2026 | 20 Oct 2026 | 3 workdays | 2.0 |
| A1190 | Practical Completion | 21 Oct 2026 | 21 Oct 2026 | 0 workdays | 0 |
Procurement Schedule
| ID | Procurement Activity | Start | Finish | Duration | Responsible |
|---|---|---|---|---|---|
| A1050 | Procure drainage pits and pipework | 15 Sep 2026 | 22 Sep 2026 | 7 workdays | Procurement Coordinator |
| A1060 | Procure reinforcement, formwork and embeds | 15 Sep 2026 | 19 Sep 2026 | 5 workdays | Procurement Coordinator |
Schedule Basis and Assumptions
Working calendarMonday, Tuesday, Wednesday, Thursday, Friday, Saturday
Hours per day10.0
Calendar exceptions
- 05-Oct-2026 — Non-working: Client operational shutdown — no contractor access (All work areas)
Key assumptions
- Client provides uninterrupted access to the work zone and responds to submitted documents within two working days.
- Existing underground services are assumed to match the client drawings
- contaminated material and latent conditions are excluded.
Schedule Health Check
| Check | Result | Status |
|---|---|---|
| Logic-linked activities | 25 links across 20 activities | Pass |
| Open start points | 1 starting point(s) | Pass |
| Open finish points | 1 finishing point(s) | Pass |
| Contract completion | 2 working day(s) buffer | Pass |