3A Project Intelligence

Overall Schedule Health Score

A single, overall assessment of schedule structure, logic, dates, float, constraints, resources and calendars.

58/100
POOR

Executive Summary

Translates the detailed checks into a concise management view of schedule reliability, exposure and immediate priorities.

6Management Actions
6High-Priority Actions
10Applicable DCMA-Aligned Checks

GOLDEN EAGLE WATER INFRASTRUCTURE is rated Poor with a calculated health score of 58, based only on information available in the uploaded schedule. The separate DCMA-aligned review applied 10 single-schedule checks. The schedule has material control weaknesses and should not yet be relied on as a dependable management forecast. The highest priorities are: Resolve negative float; Repair critical-path logic gaps; Close current forecast logic gaps.

View Management Actions Analyse Your Schedule Explore Editable Basis of Schedule

Schedule Improvement Plan

Shows where the score was lost, why it matters and the practical corrections that can improve the next schedule submission.

58/100Overall Schedule Health Score
Up to 42Improvement Opportunity
3Priority Areas

Weighted score across the health areas that can be assessed from one uploaded schedule. Missing information is marked Data not available and is excluded; it never creates a failure or score penalty.

Logic & Network17.0/25
Critical Path & Float10.0/20
Dates & Status15.0/15
Duration & Detail0/15
Constraints10.0/10
Resources & Calendars6.0/15
Health AreaScore ContributionImprovement OpportunityStatusWhat We FoundHow to Improve
Logic & Network 17.0/25 Up to 8.0 points Needs Review 2 whole-schedule and 1 current logic gaps; 0 leads, 0 lags and 0.0% non-FS relationships. Close genuine logic gaps and replace avoidable leads, lags and complex links. View findings
Critical Path & Float 10.0/20 Up to 10.0 points Priority 2 negative-float and 0 high-float activities; 4 priority findings on the reported driving path. Resolve driving-path findings and validate high-float work by WBS. View findings
Dates & Status 15.0/15 Up to 0.0 points Healthy 0 invalid-date activities and 0 with actual dates after the data date. Correct status and date integrity issues before relying on the forecast. View findings
Duration & Detail 0/15 Up to 15 points Priority 4 long-duration and 5 insufficient-detail activities. Break broad work into measurable activities with clear completion points. View findings
Constraints 10.0/10 Up to 0.0 points Healthy 0 hard, 0 dated soft and 0 ALAP constraint settings. Confirm contractual constraints and remove unnecessary date controls. View findings
Resources & Calendars 6.0/15 Up to 9.0 points Priority 40.0% resource coverage; 0 unusual calendars, 0 missing and 0 undefined calendar assignments. Complete resource loading and confirm activity calendars and exceptions. View findings

Project Overview

Confirms the schedule identity, reporting cut-off date and the volume of planning data assessed.

Project NameGOLDEN EAGLE WATER INFRASTRUCTURE
Project ID47357
SourcePrimavera P6 — Primavera P6 XER (.xer)
Data Date14-Jul-2026 06:00
Activities8
Relationships7
Resources2
Calendars1

Top Issues and Benchmarks

Prioritises the findings that matter most. Each item shows the affected population, the benchmark used and the next practical action.

Current Forecast Logic — High

1 incomplete discrete activities have missing logic (16.7%).

Disconnected work can move without correctly affecting the project forecast finish.

Benchmark: Single-schedule benchmark: no more than 5%; management target: zero unexplained open ends.

Recommended response: Add valid predecessors or successors and retain only documented boundary exceptions. View findings

Resource Coverage — High

3 of 5 eligible activities have no resource or role assignment (60.0%).

Missing assignments can understate future labour, cost and quantity demand.

Benchmark: Management target: at least 95% coverage, prioritising critical and near-critical work.

Recommended response: Assign resources or roles to genuine delivery activities, starting with the critical path. View findings

Long-Duration Activities — Moderate

4 incomplete activities exceed 44 working days (80.0%).

Long activities reduce progress visibility and delay early warning of slippage.

Benchmark: Benchmark: no more than 5% of eligible incomplete activities.

Recommended response: Break broad work into measurable control activities with clear completion points. View findings

Look-Ahead Delivery Analytics

Shows work due to start or finish soon, highlighting overdue activities and potential delivery blockers.

412-Week Activities
2Critical Activities
2Potential Blockers
0Overdue Activities

The 12-week outlook contains 4 activities, including 2 critical activities and 2 with potential delivery blockers. 0 incomplete activities have a forecast start or finish before the data date.

Open Look-Ahead

S-Curves & Progress Analytics

Compares earned, actual and forecast labour or cost using data genuinely available in the uploaded schedule.

Labour S-Curve data not available in the uploaded schedule.

Weekly Manning

Estimates the average workforce required each week from budgeted labour hours and each activity's assigned calendar.

4.9Peak Average Manning
09-Aug-2026Peak Week

Weekly labour demand is calculated from exported labour-resource target hours using each activity's assigned calendar and calendar exceptions.

Open Weekly Manning

Schedule Distribution Analytics

Shows how activity status, float and remaining duration are distributed so unusual concentrations are easy to identify.

5Low-Float Activities
0High-Float Activities
4Long Remaining Durations

5 incomplete activities (83.3% of assessed float values) have 10 working days or less total float. 4 executable activities (80.0% of assessed durations) have more than 44 working days remaining.

Open Histograms

Resource Loading Coverage

Checks whether incomplete delivery activities have resources or roles assigned. It measures coverage, not workforce capacity.

40.0%Coverage
2Resourced Activities
3Unresourced Activities

2 of 5 eligible incomplete activities (40.0%) have a resource or role assignment. 3 activities have no assignment.

Open Resource Analytics to review weekly demand by labour resource using activity-calendar working hours.

Priority Unresourced Activities

Activity IDActivity NameStatusTotal Float (Days)Critical
GE-1200Site establishmentIn Progress-5.0Yes
GE-1600Testing and commissioningNot Started0.0Yes
GE-1500Pump station constructionNot Started15.0No
Open Resource Analytics

DCMA-Aligned Schedule Quality Checks

Applies the schedule-quality checks that can be assessed from one file. Baseline comparison and native scheduling tests belong in the comparison workflow.

70/100DCMA-Aligned Check Score
10Applicable Checks
7Passed
3Need Correction

10 single-schedule checks were applicable: 7 passed, 0 need review and 3 failed. The remaining 4 checks require an approved baseline comparison, source data that was not exported, or a native scheduling-engine test.

Equal weighting of testable DCMA checks: Pass = 1 point, Review = 0.5 points and Fail = 0 points. Not Tested checks are excluded from the calculated score.

The DCMA-Aligned Check Score uses a separate pass/fail assessment method and may differ from the Overall Schedule Health Score.

CheckResultThresholdStatusBasis
1. Logic 1 (16.7%) <= 5% Fail Incomplete discrete activities missing a predecessor or successor; Level of Effort and WBS Summary activities excluded
2. Leads 0 (0.0%) 0% Pass Relationships with negative lag
3. Lags 0 (0.0%) <= 5% Pass Relationships with positive lag
4. Relationship Types 0 (0.0%) <= 10% non-FS Pass Relationships that are not Finish-to-Start
5. Hard Constraints 0 (0.0%) <= 5% Pass Start On or Finish On constraints
6. High Float 0 (0.0%) <= 5% Pass Incomplete activities with more than 44 working days of float
7. Negative Float 2 (33.3%) 0% Fail Incomplete activities with negative total float
8. High Duration 4 (80.0%) <= 5% Fail Incomplete task or resource-dependent activities longer than 44 working days
9. Invalid Dates 0 0 Pass Inconsistent dates or actual dates after the data date
10. Resources 2 (40.0%) Informational Pass Eligible incomplete activities with resource assignments

Schedule Dates & Duration Analysis

Checks reporting dates and activity durations for conditions that can hide slippage or weaken progress measurement.

Project Start12-Jan-2026
Data Date14-Jul-2026 06:00
Forecast Finish27-Aug-2027
4Long Durations
5Insufficient Detail
0Invalid Dates
0Future Actual Dates

4 activities need date or duration review: 4 exceed 44 working days, 0 have inconsistent values, and 0 contain actual dates after the data date.

5 activities (83.3%) have an original duration of at least 59.2 days, equal to 10% of the 592.5-day activity date span.

Activity IDActivity NameStatusOriginal DurationRemaining DurationStartFinishIssue
GE-1500 Pump station construction Not Started 180.0 days 180.0 days Not found Not found Original duration exceeds 44 working days
GE-1400 Pipeline installation Not Started 150.0 days 150.0 days Not found Not found Original duration exceeds 44 working days
GE-1300 Trunk main earthworks Not Started 120.0 days 120.0 days Not found Not found Original duration exceeds 44 working days
GE-1600 Testing and commissioning Not Started 60.0 days 60.0 days Not found Not found Original duration exceeds 44 working days

Longest Path & Driving Path Analysis

Identifies the chain of work most likely to control the forecast finish and the issues that could make that path unreliable.

4Path Activities
190.0Remaining Working Days
1Milestones
4Activities at Risk

4 activities are identified using Lowest-float critical activity fallback, with 190.0 total remaining working days across the listed activities. 4 activities contain logic, constraint, float, resource or date findings.

Method: Lowest-float critical activity fallback

No Primavera float-path or driving-path designation was exported. Critical activities are shown chronologically; this is not a calculated longest-path sequence.

Missing Logic1
Constrained Activities0
Unresourced Activities2
Negative Float Activities2
OrderActivity IDActivity NameStatusStartFinishRemaining DaysTotal FloatLink from PriorLagRisk
1 GE-1200 Site establishment In Progress 15-Jul-2026 28-Jul-2026 10.0 -5.0 Path start 0 days Unresourced, Negative float
2 GE-1300 Trunk main earthworks Not Started 29-Jul-2026 29-Jan-2027 120.0 -3.0 Finish-to-Start 0.0 days Negative float
3 GE-1600 Testing and commissioning Not Started 31-May-2027 20-Aug-2027 60.0 0.0 No direct link to prior row 0 days Unresourced
4 GE-9000 Practical completion Not Started 27-Aug-2027 27-Aug-2027 0.0 0.0 Finish-to-Start 0.0 days Missing logic

Critical Path Analysis

Highlights activities with little or no scheduling flexibility and the milestones most exposed to delay.

4Critical Activities
1Near-Critical Activities
66.7%Critical Percentage
1Critical Milestones

4 incomplete activities (66.7%) are critical and 1 are near-critical with up to 10 working days of float. 1 critical activities have missing logic and 0 are constrained.

Method: Total Float <= 0 hours

Activity IDActivity NameStatusTypeTotal Float (Days)Risk
GE-1200 Site establishment In Progress Resource Dependent Activity -5.0 Critical
GE-1300 Trunk main earthworks Not Started Resource Dependent Activity -3.0 Critical
GE-1600 Testing and commissioning Not Started Activity 0.0 Critical
GE-9000 Practical completion Not Started Start Milestone 0.0 Critical, Missing logic
GE-1400 Pipeline installation Not Started Resource Dependent Activity 1.0 Near-critical

Logic & Relationship Analysis

Reviews how activities are connected, including complex links, leads and lags that can make the forecast difficult to trust.

7Relationships
0.88Relationships per Activity
1.75Logic Connections per Activity
0.0%Non-FS Logic
0Leads & Lags
0Merge Hotspots

7 relationships equal 0.88 relationships per activity and 1.75 predecessor/successor connections per activity. 0 (0.0%) are not Finish-to-Start and 0 (0.0%) contain leads or lags. 0 discrete activities have three or more predecessors.

Finish-to-Start7
Start-to-Start0
Finish-to-Finish0
Start-to-Finish0
Activities affected by positive lag0
Activities affected by negative lag0
Highly connected activities (>10 total links)0
PredecessorSuccessorRelationshipLag (Days)Finding
GE-1000 - Notice to Proceed GE-1100 - Detailed design and approvals Finish-to-Start 0.0 Standard relationship
GE-1100 - Detailed design and approvals GE-1200 - Site establishment Finish-to-Start 0.0 Standard relationship
GE-1200 - Site establishment GE-1300 - Trunk main earthworks Finish-to-Start 0.0 Standard relationship
GE-1300 - Trunk main earthworks GE-1400 - Pipeline installation Finish-to-Start 0.0 Standard relationship
GE-1400 - Pipeline installation GE-1500 - Pump station construction Finish-to-Start 0.0 Standard relationship
GE-1500 - Pump station construction GE-1600 - Testing and commissioning Finish-to-Start 0.0 Standard relationship
GE-1600 - Testing and commissioning GE-9000 - Practical completion Finish-to-Start 0.0 Standard relationship

Logic Gap Analysis

Finds activities that are not properly connected to the schedule network and may move without affecting the project finish.

2Whole Schedule Gaps
1Current Forecast Gaps
0Current Missing Predecessors
1Current Missing Successors

2 discrete activities (25.0%) have missing predecessor or successor logic across the whole schedule, including completed work. Level of Effort and WBS Summary activities are excluded.

1 incomplete discrete activities (16.7%) have missing logic. Level of Effort and WBS Summary activities are excluded from this current-forecast measure.

Activity IDActivity NameStatusTypeIssue
GE-9000 Practical completion Not Started Start Milestone Missing successor

Constraints Analysis

Shows date controls applied to activities and distinguishes hard constraints from softer planning restrictions.

0Activities Affected
0Hard Constraints
0Dated Soft Constraints
0As Late As Possible

No date constraints were found on incomplete activities.

Float Analysis

Shows where the programme has no contingency, limited flexibility or unusually high float that may signal weak logic.

2Negative Float
2Zero Float
1Low Float
1Normal Float
0High Float

4 of 6 assessed activities (66.7%) have negative, zero or high float and warrant management review.

Activity IDActivity NameStatusTotal Float (Days)Float BandRisk
GE-1200 Site establishment In Progress -5.0 Negative Float Forecast dates are under pressure
GE-1300 Trunk main earthworks Not Started -3.0 Negative Float Forecast dates are under pressure
GE-1600 Testing and commissioning Not Started 0.0 Zero Float No available schedule contingency
GE-9000 Practical completion Not Started 0.0 Zero Float No available schedule contingency
GE-1400 Pipeline installation Not Started 1.0 Low Float Limited schedule contingency
GE-1500 Pump station construction Not Started 15.0 Normal Float Float is within the review range

Calendar Analysis

Checks the working weeks, shifts and exceptions that directly affect activity dates and resource demand.

1Calendars
0Unusual Patterns
0Activities Affected
0Unused Calendars

1 calendars were found; 0 use extended or unusual working patterns. 0 incomplete activities use those calendars.

CalendarTypeHours/DayHours/WeekNominal Days/WeekExceptionsActivitiesFinding
5 Day Project Calendar Calendar 8.0 40.0 5.0 0 6 No immediate issue identified

Management Action Plan

Provides the detailed, prioritised corrections behind the Executive Summary and Improvement Plan.

Recommended Management Actions

Lists the highest-value corrections in priority order so the planning team can improve the next submission.

PriorityFindingEvidenceWhy It MattersRecommended Action
Critical Resolve negative float 2 incomplete activities have negative total float. Contractual or management dates may not be achievable under the current plan. Review the driving paths, imposed dates and recovery options, then agree accountable actions.
Critical Repair critical-path logic gaps 1 critical activities have missing logic. The reported critical path may be incomplete or misleading. Add valid predecessors or successors and recalculate the schedule before accepting the critical path.
Critical Close current forecast logic gaps 1 incomplete discrete activities have missing predecessors or successors. Disconnected work can move without correctly affecting the forecast finish. Assign planning engineers to validate and close each genuine logic gap.
High Break down long-duration activities 4 incomplete activities exceed 44 working days. Long activities reduce progress visibility and delay early warning of slippage. Split major work into measurable control activities with clear handoffs and ownership.
High Complete resource loading 3 eligible incomplete activities have no resource or role assignment. Capacity, cost and manpower forecasts may understate future demand. Prioritise critical and near-critical activities, then assign accountable resources or roles.
High Improve schedule detail 5 activities are at least 10% of the exported activity date span. Broad activities can conceal slippage and make progress reporting subjective. Break down the highest-risk activities into measurable deliverables with clear completion points.

Positive Controls

Recognises schedule controls that are working well and should be preserved during corrective action.

Assessment limitation: 4 additional DCMA checks require an approved baseline comparison or a native scheduling-engine sensitivity test. Missing data is not treated as a failure.

Open Resource Analytics