Look-Ahead Delivery Analytics

Focuses attention on work due to start or finish soon, including overdue activities and possible delivery blockers.

The 12-week outlook contains 56 activities, including 23 critical activities and 0 with potential delivery blockers. 0 incomplete activities have a forecast start or finish before the data date.

12-Week Activities

56

Critical Activities

23

Potential Blockers

0

Overdue Activities

0

Look-ahead periods use the current forecast dates exported in the XER. This is not a baseline variance assessment and does not recalculate the schedule.

Delivery Windows

Summarises the workload and critical activities expected within the next 2, 4, 6 and 12 weeks.

2-Week Outlook

19

To 15-Sep-2026

Forecast Starts: 12

Forecast Finishes: 16

Critical: 6

Potential Blockers: 0

4-Week Outlook

29

To 29-Sep-2026

Forecast Starts: 22

Forecast Finishes: 22

Critical: 9

Potential Blockers: 0

6-Week Outlook

32

To 13-Oct-2026

Forecast Starts: 25

Forecast Finishes: 25

Critical: 12

Potential Blockers: 0

12-Week Outlook

56

To 24-Nov-2026

Forecast Starts: 49

Forecast Finishes: 53

Critical: 23

Potential Blockers: 0

Current Forecast Exceptions

Identifies activities already behind the reporting cut-off or missing the dates needed for reliable short-term planning.

Overdue Starts

0

Overdue Finishes

0

Missing or Invalid Dates

0

12-Week Forecast Finishes

53

Priority Activity List

Use the buttons to focus the cumulative delivery window. The web table shows the first 500 priority activities; the CSV includes the complete 12-week outlook.

Activity IDActivity NameStatusForecast Start Forecast FinishFloat DaysPotential BlockersDelivery Status
GEWIP-020206-050 Vendor Design - Issue for Client Review In Progress 28-Aug-2026 03-Sep-2026 0.0 None identified Critical
GEWIP-01-030 Construction Start Milestone Not Started 04-Sep-2026 04-Sep-2026 0.0 None identified Critical
GEWIP-050101-010 Site Preparation - Release Work Area Not Started 05-Sep-2026 06-Sep-2026 0.0 None identified Critical
GEWIP-050101-020 Site Preparation - Complete Survey and Set-Out Not Started 07-Sep-2026 09-Sep-2026 0.0 None identified Critical
GEWIP-050101-030 Site Preparation - Install Erosion and Sediment Controls Not Started 10-Sep-2026 13-Sep-2026 0.0 None identified Critical
GEWIP-050101-040 Site Preparation - Clear and Grub Not Started 14-Sep-2026 20-Sep-2026 0.0 None identified Critical
GEWIP-05030104-010 Road and Service Crossings - Complete Survey and Set-Out Not Started 05-Sep-2026 07-Sep-2026 211.2 None identified Planned
GEWIP-05030205-010 Plant Utility Services - Approve Installation Work Pack Not Started 05-Sep-2026 09-Sep-2026 247.5 None identified Planned
GEWIP-030102-040 Pumps and Mechanical Equipment - Approve Vendor Documentation In Progress 21-Aug-2026 10-Sep-2026 94.0 None identified Planned
GEWIP-030103-040 Pipes Valves and Fittings - Approve Vendor Documentation In Progress 21-Aug-2026 10-Sep-2026 90.0 None identified Planned
GEWIP-05030205-020 Plant Utility Services - Receive and Inspect Equipment Not Started 10-Sep-2026 11-Sep-2026 247.5 None identified Planned
GEWIP-030101-040 Treatment Process Equipment - Approve Vendor Documentation In Progress 25-Aug-2026 14-Sep-2026 116.0 None identified Planned
GEWIP-030104-040 Electrical Equipment - Approve Vendor Documentation In Progress 25-Aug-2026 14-Sep-2026 49.0 None identified Planned
GEWIP-030105-040 Instruments and SCADA Equipment - Approve Vendor Documentation In Progress 25-Aug-2026 14-Sep-2026 103.0 None identified Planned
GEWIP-030106-040 Structural Steel and Buildings - Approve Vendor Documentation In Progress 25-Aug-2026 14-Sep-2026 102.0 None identified Planned
GEWIP-05030104-020 Road and Service Crossings - Clear Pipeline Corridor Not Started 08-Sep-2026 14-Sep-2026 211.2 None identified Planned
GEWIP-05030205-030 Plant Utility Services - Prepare Foundations Not Started 12-Sep-2026 14-Sep-2026 247.5 None identified Planned
GEWIP-030102-050 Pumps and Mechanical Equipment - Complete Manufacture and Inspection Not Started 11-Sep-2026 12-Nov-2026 94.0 None identified Planned
GEWIP-030103-050 Pipes Valves and Fittings - Complete Manufacture and Inspection Not Started 11-Sep-2026 12-Nov-2026 90.0 None identified Planned
GEWIP-050101-050 Site Preparation - Strip and Stockpile Topsoil Not Started 21-Sep-2026 25-Sep-2026 0.0 None identified Critical
GEWIP-050102-010 Bulk Earthworks - Release Work Area Not Started 26-Sep-2026 27-Sep-2026 0.0 None identified Critical
GEWIP-050102-020 Bulk Earthworks - Complete Survey and Set-Out Not Started 28-Sep-2026 30-Sep-2026 0.0 None identified Critical
GEWIP-05030104-030 Road and Service Crossings - Excavate Trench Not Started 15-Sep-2026 21-Sep-2026 211.2 None identified Planned
GEWIP-05030205-040 Plant Utility Services - Install Major Equipment Not Started 15-Sep-2026 21-Sep-2026 247.5 None identified Planned
GEWIP-05030104-040 Road and Service Crossings - Place Pipe Bedding Not Started 22-Sep-2026 25-Sep-2026 211.2 None identified Planned
GEWIP-030101-050 Treatment Process Equipment - Complete Manufacture and Inspection Not Started 15-Sep-2026 16-Nov-2026 116.0 None identified Planned
GEWIP-030104-050 Electrical Equipment - Complete Manufacture and Inspection Not Started 15-Sep-2026 16-Nov-2026 49.0 None identified Planned
GEWIP-030105-050 Instruments and SCADA Equipment - Complete Manufacture and Inspection Not Started 15-Sep-2026 16-Nov-2026 103.0 None identified Planned
GEWIP-030106-050 Structural Steel and Buildings - Complete Manufacture and Inspection Not Started 15-Sep-2026 16-Nov-2026 102.0 None identified Planned
GEWIP-050102-030 Bulk Earthworks - Install Erosion and Sediment Controls Not Started 01-Oct-2026 04-Oct-2026 0.0 None identified Critical
GEWIP-050102-040 Bulk Earthworks - Clear and Grub Not Started 05-Oct-2026 11-Oct-2026 0.0 None identified Critical
GEWIP-050102-050 Bulk Earthworks - Strip and Stockpile Topsoil Not Started 12-Oct-2026 16-Oct-2026 0.0 None identified Critical
GEWIP-050102-060 Bulk Earthworks - Complete Bulk Earthworks Not Started 17-Oct-2026 28-Oct-2026 0.0 None identified Critical
GEWIP-050103-010 Concrete and Foundations - Release Foundation Area Not Started 29-Oct-2026 29-Oct-2026 0.0 None identified Critical
GEWIP-050103-020 Concrete and Foundations - Complete Survey and Set-Out Not Started 30-Oct-2026 31-Oct-2026 0.0 None identified Critical
GEWIP-050103-030 Concrete and Foundations - Excavate Foundations Not Started 01-Nov-2026 05-Nov-2026 0.0 None identified Critical
GEWIP-050103-040 Concrete and Foundations - Place Blinding Concrete Not Started 06-Nov-2026 07-Nov-2026 0.0 None identified Critical
GEWIP-050103-050 Concrete and Foundations - Install Below-Ground Services Not Started 08-Nov-2026 10-Nov-2026 0.0 None identified Critical
GEWIP-050103-060 Concrete and Foundations - Install Formwork Not Started 11-Nov-2026 14-Nov-2026 0.0 None identified Critical
GEWIP-050103-070 Concrete and Foundations - Install Reinforcement Not Started 15-Nov-2026 18-Nov-2026 0.0 None identified Critical
GEWIP-050103-080 Concrete and Foundations - Install Embedded Items Not Started 19-Nov-2026 20-Nov-2026 0.0 None identified Critical
GEWIP-050103-090 Concrete and Foundations - Complete Pre-Pour Inspection Not Started 21-Nov-2026 21-Nov-2026 0.0 None identified Critical
GEWIP-050103-100 Concrete and Foundations - Place Concrete Not Started 22-Nov-2026 23-Nov-2026 0.0 None identified Critical
GEWIP-05030301-010 Roads and Drainage - Release Work Area Not Started 29-Oct-2026 30-Oct-2026 146.2 None identified Planned
GEWIP-05030301-020 Roads and Drainage - Complete Survey and Set-Out Not Started 31-Oct-2026 02-Nov-2026 146.2 None identified Planned
GEWIP-05030301-030 Roads and Drainage - Excavate Not Started 03-Nov-2026 07-Nov-2026 146.2 None identified Planned
GEWIP-05030301-040 Roads and Drainage - Prepare Subgrade Not Started 08-Nov-2026 10-Nov-2026 146.2 None identified Planned
GEWIP-05030101-010 Raw Water Pipeline - Complete Survey and Set-Out Not Started 13-Nov-2026 15-Nov-2026 112.5 None identified Planned
GEWIP-05030102-010 Treated Water Pipeline - Complete Survey and Set-Out Not Started 13-Nov-2026 15-Nov-2026 120.0 None identified Planned
GEWIP-05030201-010 High Voltage Supply - Approve Electrical Work Pack Not Started 17-Nov-2026 21-Nov-2026 61.2 None identified Planned
GEWIP-05030101-020 Raw Water Pipeline - Clear Pipeline Corridor Not Started 16-Nov-2026 22-Nov-2026 112.5 None identified Planned
GEWIP-05030102-020 Treated Water Pipeline - Clear Pipeline Corridor Not Started 16-Nov-2026 22-Nov-2026 120.0 None identified Planned
GEWIP-030106-060 Structural Steel and Buildings - Deliver to Site Not Started 17-Nov-2026 23-Nov-2026 102.0 None identified Planned
GEWIP-05030201-020 High Voltage Supply - Receive Electrical Equipment Not Started 22-Nov-2026 24-Nov-2026 61.2 None identified Planned
GEWIP-05030101-030 Raw Water Pipeline - Excavate Trench Not Started 23-Nov-2026 29-Nov-2026 112.5 None identified Planned
GEWIP-05030102-030 Treated Water Pipeline - Excavate Trench Not Started 23-Nov-2026 29-Nov-2026 120.0 None identified Planned