Look-Ahead Delivery Analytics
Focuses attention on work due to start or finish soon, including overdue activities and possible delivery blockers.
The 12-week outlook contains 56 activities, including 23 critical activities and 0 with potential delivery blockers. 0 incomplete activities have a forecast start or finish before the data date.
12-Week Activities
56
Critical Activities
23
Potential Blockers
0
Overdue Activities
0
Delivery Windows
Summarises the workload and critical activities expected within the next 2, 4, 6 and 12 weeks.
2-Week Outlook
To 15-Sep-2026
Forecast Starts: 12
Forecast Finishes: 16
Critical: 6
Potential Blockers: 0
4-Week Outlook
To 29-Sep-2026
Forecast Starts: 22
Forecast Finishes: 22
Critical: 9
Potential Blockers: 0
6-Week Outlook
To 13-Oct-2026
Forecast Starts: 25
Forecast Finishes: 25
Critical: 12
Potential Blockers: 0
12-Week Outlook
To 24-Nov-2026
Forecast Starts: 49
Forecast Finishes: 53
Critical: 23
Potential Blockers: 0
Current Forecast Exceptions
Identifies activities already behind the reporting cut-off or missing the dates needed for reliable short-term planning.
Overdue Starts
0
Overdue Finishes
0
Missing or Invalid Dates
0
12-Week Forecast Finishes
53
Priority Activity List
Use the buttons to focus the cumulative delivery window. The web table shows the first 500 priority activities; the CSV includes the complete 12-week outlook.
| Activity ID | Activity Name | Status | Forecast Start | Forecast Finish | Float Days | Potential Blockers | Delivery Status |
|---|---|---|---|---|---|---|---|
| GEWIP-020206-050 | Vendor Design - Issue for Client Review | In Progress | 28-Aug-2026 | 03-Sep-2026 | 0.0 | None identified | Critical |
| GEWIP-01-030 | Construction Start Milestone | Not Started | 04-Sep-2026 | 04-Sep-2026 | 0.0 | None identified | Critical |
| GEWIP-050101-010 | Site Preparation - Release Work Area | Not Started | 05-Sep-2026 | 06-Sep-2026 | 0.0 | None identified | Critical |
| GEWIP-050101-020 | Site Preparation - Complete Survey and Set-Out | Not Started | 07-Sep-2026 | 09-Sep-2026 | 0.0 | None identified | Critical |
| GEWIP-050101-030 | Site Preparation - Install Erosion and Sediment Controls | Not Started | 10-Sep-2026 | 13-Sep-2026 | 0.0 | None identified | Critical |
| GEWIP-050101-040 | Site Preparation - Clear and Grub | Not Started | 14-Sep-2026 | 20-Sep-2026 | 0.0 | None identified | Critical |
| GEWIP-05030104-010 | Road and Service Crossings - Complete Survey and Set-Out | Not Started | 05-Sep-2026 | 07-Sep-2026 | 211.2 | None identified | Planned |
| GEWIP-05030205-010 | Plant Utility Services - Approve Installation Work Pack | Not Started | 05-Sep-2026 | 09-Sep-2026 | 247.5 | None identified | Planned |
| GEWIP-030102-040 | Pumps and Mechanical Equipment - Approve Vendor Documentation | In Progress | 21-Aug-2026 | 10-Sep-2026 | 94.0 | None identified | Planned |
| GEWIP-030103-040 | Pipes Valves and Fittings - Approve Vendor Documentation | In Progress | 21-Aug-2026 | 10-Sep-2026 | 90.0 | None identified | Planned |
| GEWIP-05030205-020 | Plant Utility Services - Receive and Inspect Equipment | Not Started | 10-Sep-2026 | 11-Sep-2026 | 247.5 | None identified | Planned |
| GEWIP-030101-040 | Treatment Process Equipment - Approve Vendor Documentation | In Progress | 25-Aug-2026 | 14-Sep-2026 | 116.0 | None identified | Planned |
| GEWIP-030104-040 | Electrical Equipment - Approve Vendor Documentation | In Progress | 25-Aug-2026 | 14-Sep-2026 | 49.0 | None identified | Planned |
| GEWIP-030105-040 | Instruments and SCADA Equipment - Approve Vendor Documentation | In Progress | 25-Aug-2026 | 14-Sep-2026 | 103.0 | None identified | Planned |
| GEWIP-030106-040 | Structural Steel and Buildings - Approve Vendor Documentation | In Progress | 25-Aug-2026 | 14-Sep-2026 | 102.0 | None identified | Planned |
| GEWIP-05030104-020 | Road and Service Crossings - Clear Pipeline Corridor | Not Started | 08-Sep-2026 | 14-Sep-2026 | 211.2 | None identified | Planned |
| GEWIP-05030205-030 | Plant Utility Services - Prepare Foundations | Not Started | 12-Sep-2026 | 14-Sep-2026 | 247.5 | None identified | Planned |
| GEWIP-030102-050 | Pumps and Mechanical Equipment - Complete Manufacture and Inspection | Not Started | 11-Sep-2026 | 12-Nov-2026 | 94.0 | None identified | Planned |
| GEWIP-030103-050 | Pipes Valves and Fittings - Complete Manufacture and Inspection | Not Started | 11-Sep-2026 | 12-Nov-2026 | 90.0 | None identified | Planned |
| GEWIP-050101-050 | Site Preparation - Strip and Stockpile Topsoil | Not Started | 21-Sep-2026 | 25-Sep-2026 | 0.0 | None identified | Critical |
| GEWIP-050102-010 | Bulk Earthworks - Release Work Area | Not Started | 26-Sep-2026 | 27-Sep-2026 | 0.0 | None identified | Critical |
| GEWIP-050102-020 | Bulk Earthworks - Complete Survey and Set-Out | Not Started | 28-Sep-2026 | 30-Sep-2026 | 0.0 | None identified | Critical |
| GEWIP-05030104-030 | Road and Service Crossings - Excavate Trench | Not Started | 15-Sep-2026 | 21-Sep-2026 | 211.2 | None identified | Planned |
| GEWIP-05030205-040 | Plant Utility Services - Install Major Equipment | Not Started | 15-Sep-2026 | 21-Sep-2026 | 247.5 | None identified | Planned |
| GEWIP-05030104-040 | Road and Service Crossings - Place Pipe Bedding | Not Started | 22-Sep-2026 | 25-Sep-2026 | 211.2 | None identified | Planned |
| GEWIP-030101-050 | Treatment Process Equipment - Complete Manufacture and Inspection | Not Started | 15-Sep-2026 | 16-Nov-2026 | 116.0 | None identified | Planned |
| GEWIP-030104-050 | Electrical Equipment - Complete Manufacture and Inspection | Not Started | 15-Sep-2026 | 16-Nov-2026 | 49.0 | None identified | Planned |
| GEWIP-030105-050 | Instruments and SCADA Equipment - Complete Manufacture and Inspection | Not Started | 15-Sep-2026 | 16-Nov-2026 | 103.0 | None identified | Planned |
| GEWIP-030106-050 | Structural Steel and Buildings - Complete Manufacture and Inspection | Not Started | 15-Sep-2026 | 16-Nov-2026 | 102.0 | None identified | Planned |
| GEWIP-050102-030 | Bulk Earthworks - Install Erosion and Sediment Controls | Not Started | 01-Oct-2026 | 04-Oct-2026 | 0.0 | None identified | Critical |
| GEWIP-050102-040 | Bulk Earthworks - Clear and Grub | Not Started | 05-Oct-2026 | 11-Oct-2026 | 0.0 | None identified | Critical |
| GEWIP-050102-050 | Bulk Earthworks - Strip and Stockpile Topsoil | Not Started | 12-Oct-2026 | 16-Oct-2026 | 0.0 | None identified | Critical |
| GEWIP-050102-060 | Bulk Earthworks - Complete Bulk Earthworks | Not Started | 17-Oct-2026 | 28-Oct-2026 | 0.0 | None identified | Critical |
| GEWIP-050103-010 | Concrete and Foundations - Release Foundation Area | Not Started | 29-Oct-2026 | 29-Oct-2026 | 0.0 | None identified | Critical |
| GEWIP-050103-020 | Concrete and Foundations - Complete Survey and Set-Out | Not Started | 30-Oct-2026 | 31-Oct-2026 | 0.0 | None identified | Critical |
| GEWIP-050103-030 | Concrete and Foundations - Excavate Foundations | Not Started | 01-Nov-2026 | 05-Nov-2026 | 0.0 | None identified | Critical |
| GEWIP-050103-040 | Concrete and Foundations - Place Blinding Concrete | Not Started | 06-Nov-2026 | 07-Nov-2026 | 0.0 | None identified | Critical |
| GEWIP-050103-050 | Concrete and Foundations - Install Below-Ground Services | Not Started | 08-Nov-2026 | 10-Nov-2026 | 0.0 | None identified | Critical |
| GEWIP-050103-060 | Concrete and Foundations - Install Formwork | Not Started | 11-Nov-2026 | 14-Nov-2026 | 0.0 | None identified | Critical |
| GEWIP-050103-070 | Concrete and Foundations - Install Reinforcement | Not Started | 15-Nov-2026 | 18-Nov-2026 | 0.0 | None identified | Critical |
| GEWIP-050103-080 | Concrete and Foundations - Install Embedded Items | Not Started | 19-Nov-2026 | 20-Nov-2026 | 0.0 | None identified | Critical |
| GEWIP-050103-090 | Concrete and Foundations - Complete Pre-Pour Inspection | Not Started | 21-Nov-2026 | 21-Nov-2026 | 0.0 | None identified | Critical |
| GEWIP-050103-100 | Concrete and Foundations - Place Concrete | Not Started | 22-Nov-2026 | 23-Nov-2026 | 0.0 | None identified | Critical |
| GEWIP-05030301-010 | Roads and Drainage - Release Work Area | Not Started | 29-Oct-2026 | 30-Oct-2026 | 146.2 | None identified | Planned |
| GEWIP-05030301-020 | Roads and Drainage - Complete Survey and Set-Out | Not Started | 31-Oct-2026 | 02-Nov-2026 | 146.2 | None identified | Planned |
| GEWIP-05030301-030 | Roads and Drainage - Excavate | Not Started | 03-Nov-2026 | 07-Nov-2026 | 146.2 | None identified | Planned |
| GEWIP-05030301-040 | Roads and Drainage - Prepare Subgrade | Not Started | 08-Nov-2026 | 10-Nov-2026 | 146.2 | None identified | Planned |
| GEWIP-05030101-010 | Raw Water Pipeline - Complete Survey and Set-Out | Not Started | 13-Nov-2026 | 15-Nov-2026 | 112.5 | None identified | Planned |
| GEWIP-05030102-010 | Treated Water Pipeline - Complete Survey and Set-Out | Not Started | 13-Nov-2026 | 15-Nov-2026 | 120.0 | None identified | Planned |
| GEWIP-05030201-010 | High Voltage Supply - Approve Electrical Work Pack | Not Started | 17-Nov-2026 | 21-Nov-2026 | 61.2 | None identified | Planned |
| GEWIP-05030101-020 | Raw Water Pipeline - Clear Pipeline Corridor | Not Started | 16-Nov-2026 | 22-Nov-2026 | 112.5 | None identified | Planned |
| GEWIP-05030102-020 | Treated Water Pipeline - Clear Pipeline Corridor | Not Started | 16-Nov-2026 | 22-Nov-2026 | 120.0 | None identified | Planned |
| GEWIP-030106-060 | Structural Steel and Buildings - Deliver to Site | Not Started | 17-Nov-2026 | 23-Nov-2026 | 102.0 | None identified | Planned |
| GEWIP-05030201-020 | High Voltage Supply - Receive Electrical Equipment | Not Started | 22-Nov-2026 | 24-Nov-2026 | 61.2 | None identified | Planned |
| GEWIP-05030101-030 | Raw Water Pipeline - Excavate Trench | Not Started | 23-Nov-2026 | 29-Nov-2026 | 112.5 | None identified | Planned |
| GEWIP-05030102-030 | Treated Water Pipeline - Excavate Trench | Not Started | 23-Nov-2026 | 29-Nov-2026 | 120.0 | None identified | Planned |