A single, overall assessment of schedule structure, logic, dates, float, constraints, resources and calendars.
Translates the detailed checks into a concise management view of schedule reliability, exposure and immediate priorities.
GOLDEN EAGLE WATER INFRASTRUCTURE is rated Good with a calculated health score of 90, based only on information available in the uploaded schedule. The separate DCMA-aligned review applied 10 single-schedule checks. The schedule is generally well structured, but targeted corrections remain before full reliance on the forecast. The highest priorities are: Repair critical-path logic gaps; Close current forecast logic gaps; Review excessive float.
View Management Actions Analyse Your Schedule Explore Editable Basis of ScheduleShows where the score was lost, why it matters and the practical corrections that can improve the next schedule submission.
Weighted score across the health areas that can be assessed from one uploaded schedule. Missing information is marked Data not available and is excluded; it never creates a failure or score penalty.
| Health Area | Score Contribution | Improvement Opportunity | Status | What We Found | How to Improve |
|---|---|---|---|---|---|
| Logic & Network | 23.2/25 | Up to 1.8 points | Healthy | 5 whole-schedule and 4 current logic gaps; 0 leads, 1 lags and 0.0% non-FS relationships. | Close genuine logic gaps and replace avoidable leads, lags and complex links. View findings |
| Critical Path & Float | 13.4/20 | Up to 6.6 points | Needs Review | 0 negative-float and 85 high-float activities; 2 priority findings on the reported driving path. | Resolve driving-path findings and validate high-float work by WBS. View findings |
| Dates & Status | 15.0/15 | Up to 0.0 points | Healthy | 0 invalid-date activities and 0 with actual dates after the data date. | Correct status and date integrity issues before relying on the forecast. View findings |
| Duration & Detail | 15.0/15 | Up to 0.0 points | Healthy | 6 long-duration and 6 insufficient-detail activities. | Break broad work into measurable activities with clear completion points. View findings |
| Constraints | 10.0/10 | Up to 0.0 points | Healthy | 0 hard, 0 dated soft and 0 ALAP constraint settings. | Confirm contractual constraints and remove unnecessary date controls. View findings |
| Resources & Calendars | 13.5/15 | Up to 1.5 points | Healthy | 100.0% resource coverage; 1 unusual calendars, 0 missing and 0 undefined calendar assignments. | Complete resource loading and confirm activity calendars and exceptions. View findings |
Confirms the schedule identity, reporting cut-off date and the volume of planning data assessed.
| Project Name | GOLDEN EAGLE WATER INFRASTRUCTURE |
| Project ID | 368 |
| Source | Primavera P6 — Primavera P6 XER (.xer) |
| Data Date | 01-Sep-2026 08:00 |
| Activities | 290 |
| Relationships | 331 |
| WBS Elements | 70 |
| Resources | 18 |
| Resource Assignments | 315 |
| Quantity Profiles | 7 |
| Calendars | 2 |
Prioritises the findings that matter most. Each item shows the affected population, the benchmark used and the next practical action.
85 of 196 assessed activities exceed 44 working days of float (43.4%).
A high proportion can indicate weak logic, broad constraints or unrealistic contingency.
Benchmark: Benchmark: no more than 5% of assessed incomplete activities.
Recommended response: Review high-float paths by WBS and confirm the relationships reflect the delivery strategy. View findings
4 incomplete discrete activities have missing logic (2.0%).
Disconnected work can move without correctly affecting the project forecast finish.
Benchmark: Single-schedule benchmark: no more than 5%; management target: zero unexplained open ends.
Recommended response: Add valid predecessors or successors and retain only documented boundary exceptions. View findings
Shows work due to start or finish soon, highlighting overdue activities and potential delivery blockers.
The 12-week outlook contains 56 activities, including 23 critical activities and 0 with potential delivery blockers. 0 incomplete activities have a forecast start or finish before the data date.
Open Look-AheadCompares earned, actual and forecast labour or cost using data genuinely available in the uploaded schedule.
As at 2026-09-01, 7,639.6 actual labour hours and 7,345.7 earned labour hours are reported. Forecast labour hours are 38,433.8, a variance of 0.8% against the current budgeted total.
Open S-CurvesEstimates the average workforce required each week from budgeted labour hours and each activity's assigned calendar.
Weekly labour demand is calculated from exported labour-resource target hours using each activity's assigned calendar and calendar exceptions.
Open Weekly ManningShows how activity status, float and remaining duration are distributed so unusual concentrations are easy to identify.
79 incomplete activities (40.3% of assessed float values) have 10 working days or less total float. 6 executable activities (3.1% of assessed durations) have more than 44 working days remaining.
Open HistogramsChecks whether incomplete delivery activities have resources or roles assigned. It measures coverage, not workforce capacity.
191 of 191 eligible incomplete activities (100.0%) have a resource or role assignment. 0 activities have no assignment.
Open Resource Analytics to review weekly demand by labour resource using activity-calendar working hours.
Open Resource AnalyticsApplies the schedule-quality checks that can be assessed from one file. Baseline comparison and native scheduling tests belong in the comparison workflow.
10 single-schedule checks were applicable: 9 passed, 0 need review and 1 failed. The remaining 4 checks require an approved baseline comparison, source data that was not exported, or a native scheduling-engine test.
Equal weighting of testable DCMA checks: Pass = 1 point, Review = 0.5 points and Fail = 0 points. Not Tested checks are excluded from the calculated score.
The DCMA-Aligned Check Score uses a separate pass/fail assessment method and may differ from the Overall Schedule Health Score.
| Check | Result | Threshold | Status | Basis |
|---|---|---|---|---|
| 1. Logic | 4 (2.0%) | <= 5% | Pass | Incomplete discrete activities missing a predecessor or successor; Level of Effort and WBS Summary activities excluded |
| 2. Leads | 0 (0.0%) | 0% | Pass | Relationships with negative lag |
| 3. Lags | 1 (0.3%) | <= 5% | Pass | Relationships with positive lag |
| 4. Relationship Types | 0 (0.0%) | <= 10% non-FS | Pass | Relationships that are not Finish-to-Start |
| 5. Hard Constraints | 0 (0.0%) | <= 5% | Pass | Start On or Finish On constraints |
| 6. High Float | 85 (43.4%) | <= 5% | Fail | Incomplete activities with more than 44 working days of float |
| 7. Negative Float | 0 (0.0%) | 0% | Pass | Incomplete activities with negative total float |
| 8. High Duration | 6 (3.1%) | <= 5% | Pass | Incomplete task or resource-dependent activities longer than 44 working days |
| 9. Invalid Dates | 0 | 0 | Pass | Inconsistent dates or actual dates after the data date |
| 10. Resources | 191 (100.0%) | Informational | Pass | Eligible incomplete activities with resource assignments |
Checks reporting dates and activity durations for conditions that can hide slippage or weaken progress measurement.
| Project Start | 01-Apr-2026 |
| Data Date | 01-Sep-2026 08:00 |
| Forecast Finish | 09-Jun-2027 |
6 activities need date or duration review: 6 exceed 44 working days, 0 have inconsistent values, and 0 contain actual dates after the data date.
6 activities (2.1%) have an original duration of at least 43.4 days, equal to 10% of the 434.0-day activity date span.
| Activity ID | Activity Name | Status | Original Duration | Remaining Duration | Start | Finish | Issue |
|---|---|---|---|---|---|---|---|
| GEWIP-030101-050 | Treatment Process Equipment - Complete Manufacture and Inspection | Not Started | 45.0 days | 45.0 days | 15-Sep-2026 | 16-Nov-2026 | Original duration exceeds 44 working days |
| GEWIP-030102-050 | Pumps and Mechanical Equipment - Complete Manufacture and Inspection | Not Started | 45.0 days | 45.0 days | 11-Sep-2026 | 12-Nov-2026 | Original duration exceeds 44 working days |
| GEWIP-030103-050 | Pipes Valves and Fittings - Complete Manufacture and Inspection | Not Started | 45.0 days | 45.0 days | 11-Sep-2026 | 12-Nov-2026 | Original duration exceeds 44 working days |
| GEWIP-030104-050 | Electrical Equipment - Complete Manufacture and Inspection | Not Started | 45.0 days | 45.0 days | 15-Sep-2026 | 16-Nov-2026 | Original duration exceeds 44 working days |
| GEWIP-030105-050 | Instruments and SCADA Equipment - Complete Manufacture and Inspection | Not Started | 45.0 days | 45.0 days | 15-Sep-2026 | 16-Nov-2026 | Original duration exceeds 44 working days |
| GEWIP-030106-050 | Structural Steel and Buildings - Complete Manufacture and Inspection | Not Started | 45.0 days | 45.0 days | 15-Sep-2026 | 16-Nov-2026 | Original duration exceeds 44 working days |
Identifies the chain of work most likely to control the forecast finish and the issues that could make that path unreliable.
26 activities are identified using Primavera driving activity flag, with 210.6 total remaining working days across the listed activities. 2 activities contain logic, constraint, float, resource or date findings.
Method: Primavera driving activity flag
Primavera identified the driving activities but did not export Float Path 1 order. They are displayed chronologically and should not be read as a calculated network sequence.
| Missing Logic | 2 |
| Constrained Activities | 0 |
| Unresourced Activities | 0 |
| Negative Float Activities | 0 |
| Order | Activity ID | Activity Name | Status | Start | Finish | Remaining Days | Total Float | Link from Prior | Lag | Risk |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | GEWIP-030104-040 | Electrical Equipment - Approve Vendor Documentation | In Progress | 25-Aug-2026 | 14-Sep-2026 | 9.8 | 49.0 | Path start | 0 days | No immediate issue identified |
| 2 | GEWIP-030106-040 | Structural Steel and Buildings - Approve Vendor Documentation | In Progress | 25-Aug-2026 | 14-Sep-2026 | 9.8 | 102.0 | No direct link to prior row | 0 days | No immediate issue identified |
| 3 | GEWIP-020206-050 | Vendor Design - Issue for Client Review | In Progress | 28-Aug-2026 | 03-Sep-2026 | 1.9 | 0.0 | No direct link to prior row | 0 days | No immediate issue identified |
| 4 | GEWIP-01-030 | Construction Start Milestone | Not Started | 04-Sep-2026 | 04-Sep-2026 | 0.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 5 | GEWIP-030104-050 | Electrical Equipment - Complete Manufacture and Inspection | Not Started | 15-Sep-2026 | 16-Nov-2026 | 45.0 | 49.0 | No direct link to prior row | 0 days | No immediate issue identified |
| 6 | GEWIP-030106-050 | Structural Steel and Buildings - Complete Manufacture and Inspection | Not Started | 15-Sep-2026 | 16-Nov-2026 | 45.0 | 102.0 | No direct link to prior row | 0 days | No immediate issue identified |
| 7 | GEWIP-030106-060 | Structural Steel and Buildings - Deliver to Site | Not Started | 17-Nov-2026 | 23-Nov-2026 | 5.0 | 102.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 8 | GEWIP-05020101-040 | Intake Works - Prepare Subgrade | Not Started | 01-Jan-2027 | 03-Jan-2027 | 3.0 | 161.2 | No direct link to prior row | 0 days | No immediate issue identified |
| 9 | GEWIP-05020101-120 | Intake Works - Complete Quality Records | Not Started | 29-Jan-2027 | 30-Jan-2027 | 2.0 | 161.2 | No direct link to prior row | 0 days | No immediate issue identified |
| 10 | GEWIP-05020101-130 | Intake Works - Handover Civil Works | Not Started | 31-Jan-2027 | 31-Jan-2027 | 1.0 | 161.2 | Finish-to-Start | 0.0 days | Missing logic |
| 11 | GEWIP-0601-010 | Approve Pre-Commissioning Plan | Not Started | 26-Feb-2027 | 02-Mar-2027 | 5.0 | 0.0 | No direct link to prior row | 0 days | No immediate issue identified |
| 12 | GEWIP-0601-020 | Complete System Walkdowns | Not Started | 03-Mar-2027 | 12-Mar-2027 | 10.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 13 | GEWIP-0601-030 | Close Construction Punch Items | Not Started | 13-Mar-2027 | 17-Mar-2027 | 5.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 14 | GEWIP-0601-040 | Complete Dry Functional Tests | Not Started | 18-Mar-2027 | 27-Mar-2027 | 10.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 15 | GEWIP-0601-050 | Ready for Commissioning Milestone | Not Started | 28-Mar-2027 | 28-Mar-2027 | 0.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 16 | GEWIP-0602-010 | Introduce Water to System | Not Started | 29-Mar-2027 | 31-Mar-2027 | 3.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 17 | GEWIP-0602-020 | Start Process Equipment | Not Started | 01-Apr-2027 | 05-Apr-2027 | 5.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 18 | GEWIP-0602-030 | Complete Integrated System Testing | Not Started | 06-Apr-2027 | 15-Apr-2027 | 10.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 19 | GEWIP-0602-040 | Complete Performance Test | Not Started | 16-Apr-2027 | 25-Apr-2027 | 10.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 20 | GEWIP-0602-050 | Operational Acceptance Milestone | Not Started | 26-Apr-2027 | 26-Apr-2027 | 0.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 21 | GEWIP-0603-010 | Submit Operations and Maintenance Manuals | Not Started | 27-Apr-2027 | 10-May-2027 | 10.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 22 | GEWIP-0603-020 | Complete Operator Training | Not Started | 11-May-2027 | 17-May-2027 | 5.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 23 | GEWIP-0603-030 | Submit As-Built Drawings | Not Started | 18-May-2027 | 31-May-2027 | 10.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 24 | GEWIP-0603-040 | Close Remaining Punch Items | Not Started | 01-Jun-2027 | 07-Jun-2027 | 5.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 25 | GEWIP-0603-050 | Final Handover Milestone | Not Started | 08-Jun-2027 | 08-Jun-2027 | 0.0 | 0.0 | Finish-to-Start | 0.0 days | No immediate issue identified |
| 26 | GEWIP-01-040 | Practical Completion Milestone | Not Started | 09-Jun-2027 | 09-Jun-2027 | 0.0 | 0.0 | Finish-to-Start | 0.0 days | Missing logic |
Highlights activities with little or no scheduling flexibility and the milestones most exposed to delay.
63 incomplete activities (32.1%) are critical and 16 are near-critical with up to 10 working days of float. 1 critical activities have missing logic and 0 are constrained.
Method: Total Float <= 0 hours
| Activity ID | Activity Name | Status | Type | Total Float (Days) | Risk |
|---|---|---|---|---|---|
| GEWIP-020206-050 | Vendor Design - Issue for Client Review | In Progress | Activity | 0.0 | Critical |
| GEWIP-01-030 | Construction Start Milestone | Not Started | Start Milestone | 0.0 | Critical |
| GEWIP-01-040 | Practical Completion Milestone | Not Started | Finish Milestone | 0.0 | Critical, Missing logic |
| GEWIP-050101-010 | Site Preparation - Release Work Area | Not Started | Activity | 0.0 | Critical |
| GEWIP-050101-020 | Site Preparation - Complete Survey and Set-Out | Not Started | Activity | 0.0 | Critical |
| GEWIP-050101-030 | Site Preparation - Install Erosion and Sediment Controls | Not Started | Activity | 0.0 | Critical |
| GEWIP-050101-040 | Site Preparation - Clear and Grub | Not Started | Activity | 0.0 | Critical |
| GEWIP-050101-050 | Site Preparation - Strip and Stockpile Topsoil | Not Started | Activity | 0.0 | Critical |
| GEWIP-050102-010 | Bulk Earthworks - Release Work Area | Not Started | Activity | 0.0 | Critical |
| GEWIP-050102-020 | Bulk Earthworks - Complete Survey and Set-Out | Not Started | Activity | 0.0 | Critical |
| GEWIP-050102-030 | Bulk Earthworks - Install Erosion and Sediment Controls | Not Started | Activity | 0.0 | Critical |
| GEWIP-050102-040 | Bulk Earthworks - Clear and Grub | Not Started | Activity | 0.0 | Critical |
| GEWIP-050102-050 | Bulk Earthworks - Strip and Stockpile Topsoil | Not Started | Activity | 0.0 | Critical |
| GEWIP-050102-060 | Bulk Earthworks - Complete Bulk Earthworks | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-010 | Concrete and Foundations - Release Foundation Area | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-020 | Concrete and Foundations - Complete Survey and Set-Out | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020207-010 | Plant Electrical Works - Approve Electrical Work Pack | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020207-020 | Plant Electrical Works - Receive Electrical Equipment | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020207-030 | Plant Electrical Works - Install Equipment Supports | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020207-040 | Plant Electrical Works - Install Switchboards | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020208-010 | Plant Instrumentation - Approve Control System Work Pack | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020208-020 | Plant Instrumentation - Receive Instruments and Panels | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020208-030 | Plant Instrumentation - Install Control Panels | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020208-040 | Plant Instrumentation - Install Field Instruments | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020208-050 | Plant Instrumentation - Install Instrument Cables | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020209-010 | SCADA and Control System - Approve Control System Work Pack | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020209-020 | SCADA and Control System - Receive Instruments and Panels | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020209-030 | SCADA and Control System - Install Control Panels | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020209-040 | SCADA and Control System - Install Field Instruments | Not Started | Activity | 0.0 | Critical |
| GEWIP-0601-010 | Approve Pre-Commissioning Plan | Not Started | Activity | 0.0 | Critical |
| GEWIP-0601-020 | Complete System Walkdowns | Not Started | Activity | 0.0 | Critical |
| GEWIP-0601-030 | Close Construction Punch Items | Not Started | Activity | 0.0 | Critical |
| GEWIP-0601-040 | Complete Dry Functional Tests | Not Started | Activity | 0.0 | Critical |
| GEWIP-0601-050 | Ready for Commissioning Milestone | Not Started | Finish Milestone | 0.0 | Critical |
| GEWIP-0602-010 | Introduce Water to System | Not Started | Activity | 0.0 | Critical |
| GEWIP-0602-020 | Start Process Equipment | Not Started | Activity | 0.0 | Critical |
| GEWIP-0602-030 | Complete Integrated System Testing | Not Started | Activity | 0.0 | Critical |
| GEWIP-0602-040 | Complete Performance Test | Not Started | Activity | 0.0 | Critical |
| GEWIP-0602-050 | Operational Acceptance Milestone | Not Started | Finish Milestone | 0.0 | Critical |
| GEWIP-0603-010 | Submit Operations and Maintenance Manuals | Not Started | Activity | 0.0 | Critical |
| GEWIP-0603-020 | Complete Operator Training | Not Started | Activity | 0.0 | Critical |
| GEWIP-0603-030 | Submit As-Built Drawings | Not Started | Activity | 0.0 | Critical |
| GEWIP-0603-040 | Close Remaining Punch Items | Not Started | Activity | 0.0 | Critical |
| GEWIP-0603-050 | Final Handover Milestone | Not Started | Finish Milestone | 0.0 | Critical |
| GEWIP-050103-030 | Concrete and Foundations - Excavate Foundations | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-040 | Concrete and Foundations - Place Blinding Concrete | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-050 | Concrete and Foundations - Install Below-Ground Services | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-060 | Concrete and Foundations - Install Formwork | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-070 | Concrete and Foundations - Install Reinforcement | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-080 | Concrete and Foundations - Install Embedded Items | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-090 | Concrete and Foundations - Complete Pre-Pour Inspection | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-100 | Concrete and Foundations - Place Concrete | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-110 | Concrete and Foundations - Cure Concrete | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-120 | Concrete and Foundations - Strip Formwork | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-130 | Concrete and Foundations - Complete Concrete Repairs | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-140 | Concrete and Foundations - Apply Protective Coating | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-150 | Concrete and Foundations - Backfill Foundations | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-160 | Concrete and Foundations - Install Equipment Plinths | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-170 | Concrete and Foundations - Grout Baseplates | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-180 | Concrete and Foundations - Complete Dimensional Survey | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-190 | Concrete and Foundations - Complete Quality Records | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-200 | Concrete and Foundations - Handover Foundations | Not Started | Activity | 0.0 | Critical |
| GEWIP-050103-210 | Concrete and Foundations - Close Foundation Work Pack | Not Started | Activity | 0.0 | Critical |
| GEWIP-05020206-010 | Mechanical Equipment - Approve Installation Work Pack | Not Started | Activity | 2.5 | Near-critical |
| GEWIP-05020206-020 | Mechanical Equipment - Receive and Inspect Equipment | Not Started | Activity | 2.5 | Near-critical |
| GEWIP-05020206-030 | Mechanical Equipment - Prepare Foundations | Not Started | Activity | 2.5 | Near-critical |
| GEWIP-05020206-040 | Mechanical Equipment - Install Major Equipment | Not Started | Activity | 2.5 | Near-critical |
| GEWIP-05020202-010 | Treated Water Pump Station - Approve Installation Work Pack | Not Started | Activity | 10.0 | Near-critical |
| GEWIP-05020202-020 | Treated Water Pump Station - Receive and Inspect Equipment | Not Started | Activity | 10.0 | Near-critical |
| GEWIP-05020202-030 | Treated Water Pump Station - Prepare Foundations | Not Started | Activity | 10.0 | Near-critical |
| GEWIP-05020202-040 | Treated Water Pump Station - Install Major Equipment | Not Started | Activity | 10.0 | Near-critical |
| GEWIP-05030105-010 | Surge Protection System - Complete Survey and Set-Out | Not Started | Activity | 10.0 | Near-critical |
| GEWIP-05030105-020 | Surge Protection System - Clear Pipeline Corridor | Not Started | Activity | 10.0 | Near-critical |
| GEWIP-05030105-030 | Surge Protection System - Excavate Trench | Not Started | Activity | 10.0 | Near-critical |
| GEWIP-05030105-040 | Surge Protection System - Place Pipe Bedding | Not Started | Activity | 10.0 | Near-critical |
| GEWIP-05030106-010 | Pipeline Testing and Disinfection - Complete Survey and Set-Out | Not Started | Activity | 10.0 | Near-critical |
| GEWIP-05030106-020 | Pipeline Testing and Disinfection - Clear Pipeline Corridor | Not Started | Activity | 10.0 | Near-critical |
| GEWIP-05030106-030 | Pipeline Testing and Disinfection - Excavate Trench | Not Started | Activity | 10.0 | Near-critical |
| GEWIP-05030106-040 | Pipeline Testing and Disinfection - Place Pipe Bedding | Not Started | Activity | 10.0 | Near-critical |
Reviews how activities are connected, including complex links, leads and lags that can make the forecast difficult to trust.
331 relationships equal 1.14 relationships per activity and 2.28 predecessor/successor connections per activity. 0 (0.0%) are not Finish-to-Start and 1 (0.3%) contain leads or lags. 5 discrete activities have three or more predecessors.
| Finish-to-Start | 331 |
| Start-to-Start | 0 |
| Finish-to-Finish | 0 |
| Start-to-Finish | 0 |
| Activities affected by positive lag | 1 |
| Activities affected by negative lag | 0 |
| Highly connected activities (>10 total links) | 1 |
| Predecessor | Successor | Relationship | Lag (Days) | Finding |
|---|---|---|---|---|
| GEWIP-01-010 - Notice to Proceed Milestone | GEWIP-01-020 - Baseline Schedule Approved Milestone | Finish-to-Start | 10.0 | Lag delays the linked activity |
| GEWIP-020101-010 - Preliminary Process Design - Confirm Design Criteria | GEWIP-020101-020 - Preliminary Process Design - Complete Design Calculations | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020101-020 - Preliminary Process Design - Complete Design Calculations | GEWIP-020101-030 - Preliminary Process Design - Prepare Drawings and Specifications | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020101-030 - Preliminary Process Design - Prepare Drawings and Specifications | GEWIP-020101-040 - Preliminary Process Design - Complete Interdisciplinary Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020101-040 - Preliminary Process Design - Complete Interdisciplinary Review | GEWIP-020101-050 - Preliminary Process Design - Issue for Client Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020101-050 - Preliminary Process Design - Issue for Client Review | GEWIP-020101-060 - Preliminary Process Design - Incorporate Review Comments | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020101-060 - Preliminary Process Design - Incorporate Review Comments | GEWIP-020101-070 - Preliminary Process Design - Issue for Construction | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020102-010 - Preliminary Civil Design - Confirm Design Criteria | GEWIP-020102-020 - Preliminary Civil Design - Complete Design Calculations | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020102-020 - Preliminary Civil Design - Complete Design Calculations | GEWIP-020102-030 - Preliminary Civil Design - Prepare Drawings and Specifications | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020102-030 - Preliminary Civil Design - Prepare Drawings and Specifications | GEWIP-020102-040 - Preliminary Civil Design - Complete Interdisciplinary Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020102-040 - Preliminary Civil Design - Complete Interdisciplinary Review | GEWIP-020102-050 - Preliminary Civil Design - Issue for Client Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020102-050 - Preliminary Civil Design - Issue for Client Review | GEWIP-020102-060 - Preliminary Civil Design - Incorporate Review Comments | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020102-060 - Preliminary Civil Design - Incorporate Review Comments | GEWIP-020102-070 - Preliminary Civil Design - Issue for Construction | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020103-010 - Preliminary Mechanical Design - Confirm Design Criteria | GEWIP-020103-020 - Preliminary Mechanical Design - Complete Design Calculations | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020103-020 - Preliminary Mechanical Design - Complete Design Calculations | GEWIP-020103-030 - Preliminary Mechanical Design - Prepare Drawings and Specifications | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020103-030 - Preliminary Mechanical Design - Prepare Drawings and Specifications | GEWIP-020103-040 - Preliminary Mechanical Design - Complete Interdisciplinary Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020103-040 - Preliminary Mechanical Design - Complete Interdisciplinary Review | GEWIP-020103-050 - Preliminary Mechanical Design - Issue for Client Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020103-050 - Preliminary Mechanical Design - Issue for Client Review | GEWIP-020103-060 - Preliminary Mechanical Design - Incorporate Review Comments | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020104-010 - Preliminary Electrical Design - Confirm Design Criteria | GEWIP-020104-020 - Preliminary Electrical Design - Complete Design Calculations | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020104-020 - Preliminary Electrical Design - Complete Design Calculations | GEWIP-020104-030 - Preliminary Electrical Design - Prepare Drawings and Specifications | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020104-030 - Preliminary Electrical Design - Prepare Drawings and Specifications | GEWIP-020104-040 - Preliminary Electrical Design - Complete Interdisciplinary Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020104-040 - Preliminary Electrical Design - Complete Interdisciplinary Review | GEWIP-020104-050 - Preliminary Electrical Design - Issue for Client Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020104-050 - Preliminary Electrical Design - Issue for Client Review | GEWIP-020104-060 - Preliminary Electrical Design - Incorporate Review Comments | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020104-060 - Preliminary Electrical Design - Incorporate Review Comments | GEWIP-020104-070 - Preliminary Electrical Design - Issue for Construction | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020105-010 - Environmental Approvals - Confirm Approval Requirements | GEWIP-020105-020 - Environmental Approvals - Prepare Environmental Documentation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020105-020 - Environmental Approvals - Prepare Environmental Documentation | GEWIP-020105-030 - Environmental Approvals - Submit Approval Application | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020105-030 - Environmental Approvals - Submit Approval Application | GEWIP-020105-040 - Environmental Approvals - Respond to Authority Comments | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020105-040 - Environmental Approvals - Respond to Authority Comments | GEWIP-020105-050 - Environmental Approvals - Obtain Environmental Approval | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020105-050 - Environmental Approvals - Obtain Environmental Approval | GEWIP-020105-060 - Environmental Approvals - Issue Approval Conditions | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020105-060 - Environmental Approvals - Issue Approval Conditions | GEWIP-020105-070 - Environmental Approvals - Close Approval Actions | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020201-010 - Process and Hydraulic Design - Confirm Design Criteria | GEWIP-020201-020 - Process and Hydraulic Design - Complete Design Calculations | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020201-020 - Process and Hydraulic Design - Complete Design Calculations | GEWIP-020201-030 - Process and Hydraulic Design - Prepare Drawings and Specifications | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020201-030 - Process and Hydraulic Design - Prepare Drawings and Specifications | GEWIP-020201-040 - Process and Hydraulic Design - Complete Interdisciplinary Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020201-040 - Process and Hydraulic Design - Complete Interdisciplinary Review | GEWIP-020201-050 - Process and Hydraulic Design - Issue for Client Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020201-050 - Process and Hydraulic Design - Issue for Client Review | GEWIP-020201-060 - Process and Hydraulic Design - Incorporate Review Comments | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020202-010 - Civil and Structural Design - Confirm Design Criteria | GEWIP-020202-020 - Civil and Structural Design - Complete Design Calculations | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020202-020 - Civil and Structural Design - Complete Design Calculations | GEWIP-020202-030 - Civil and Structural Design - Prepare Drawings and Specifications | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020202-030 - Civil and Structural Design - Prepare Drawings and Specifications | GEWIP-020202-040 - Civil and Structural Design - Complete Interdisciplinary Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020202-040 - Civil and Structural Design - Complete Interdisciplinary Review | GEWIP-020202-050 - Civil and Structural Design - Issue for Client Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020202-050 - Civil and Structural Design - Issue for Client Review | GEWIP-020202-060 - Civil and Structural Design - Incorporate Review Comments | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020203-010 - Mechanical and Piping Design - Confirm Design Criteria | GEWIP-020203-020 - Mechanical and Piping Design - Complete Design Calculations | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020203-020 - Mechanical and Piping Design - Complete Design Calculations | GEWIP-020203-030 - Mechanical and Piping Design - Prepare Drawings and Specifications | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020203-030 - Mechanical and Piping Design - Prepare Drawings and Specifications | GEWIP-020203-040 - Mechanical and Piping Design - Complete Interdisciplinary Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020203-040 - Mechanical and Piping Design - Complete Interdisciplinary Review | GEWIP-020203-050 - Mechanical and Piping Design - Issue for Client Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020203-050 - Mechanical and Piping Design - Issue for Client Review | GEWIP-020203-060 - Mechanical and Piping Design - Incorporate Review Comments | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020204-010 - Electrical Design - Confirm Design Criteria | GEWIP-020204-020 - Electrical Design - Complete Design Calculations | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020204-020 - Electrical Design - Complete Design Calculations | GEWIP-020204-030 - Electrical Design - Prepare Drawings and Specifications | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020204-030 - Electrical Design - Prepare Drawings and Specifications | GEWIP-020204-040 - Electrical Design - Complete Interdisciplinary Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020204-040 - Electrical Design - Complete Interdisciplinary Review | GEWIP-020204-050 - Electrical Design - Issue for Client Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020204-050 - Electrical Design - Issue for Client Review | GEWIP-020204-060 - Electrical Design - Incorporate Review Comments | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020205-010 - Instrumentation and SCADA Design - Confirm Design Criteria | GEWIP-020205-020 - Instrumentation and SCADA Design - Complete Design Calculations | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020205-020 - Instrumentation and SCADA Design - Complete Design Calculations | GEWIP-020205-030 - Instrumentation and SCADA Design - Prepare Drawings and Specifications | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020205-030 - Instrumentation and SCADA Design - Prepare Drawings and Specifications | GEWIP-020205-040 - Instrumentation and SCADA Design - Complete Interdisciplinary Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020205-040 - Instrumentation and SCADA Design - Complete Interdisciplinary Review | GEWIP-020205-050 - Instrumentation and SCADA Design - Issue for Client Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020205-050 - Instrumentation and SCADA Design - Issue for Client Review | GEWIP-020205-060 - Instrumentation and SCADA Design - Incorporate Review Comments | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020206-010 - Vendor Design - Confirm Design Criteria | GEWIP-020206-020 - Vendor Design - Complete Design Calculations | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020206-020 - Vendor Design - Complete Design Calculations | GEWIP-020206-030 - Vendor Design - Prepare Drawings and Specifications | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020206-030 - Vendor Design - Prepare Drawings and Specifications | GEWIP-020206-040 - Vendor Design - Complete Interdisciplinary Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-020206-040 - Vendor Design - Complete Interdisciplinary Review | GEWIP-020206-050 - Vendor Design - Issue for Client Review | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030101-010 - Treatment Process Equipment - Issue Request for Quotation | GEWIP-030101-020 - Treatment Process Equipment - Complete Tender Evaluation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030101-020 - Treatment Process Equipment - Complete Tender Evaluation | GEWIP-030101-030 - Treatment Process Equipment - Award Purchase Order | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030101-030 - Treatment Process Equipment - Award Purchase Order | GEWIP-030101-040 - Treatment Process Equipment - Approve Vendor Documentation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030101-040 - Treatment Process Equipment - Approve Vendor Documentation | GEWIP-030101-050 - Treatment Process Equipment - Complete Manufacture and Inspection | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030102-010 - Pumps and Mechanical Equipment - Issue Request for Quotation | GEWIP-030102-020 - Pumps and Mechanical Equipment - Complete Tender Evaluation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030102-020 - Pumps and Mechanical Equipment - Complete Tender Evaluation | GEWIP-030102-030 - Pumps and Mechanical Equipment - Award Purchase Order | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030102-030 - Pumps and Mechanical Equipment - Award Purchase Order | GEWIP-030102-040 - Pumps and Mechanical Equipment - Approve Vendor Documentation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030102-040 - Pumps and Mechanical Equipment - Approve Vendor Documentation | GEWIP-030102-050 - Pumps and Mechanical Equipment - Complete Manufacture and Inspection | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030103-010 - Pipes Valves and Fittings - Issue Request for Quotation | GEWIP-030103-020 - Pipes Valves and Fittings - Complete Tender Evaluation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030103-020 - Pipes Valves and Fittings - Complete Tender Evaluation | GEWIP-030103-030 - Pipes Valves and Fittings - Award Purchase Order | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030103-030 - Pipes Valves and Fittings - Award Purchase Order | GEWIP-030103-040 - Pipes Valves and Fittings - Approve Vendor Documentation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030103-040 - Pipes Valves and Fittings - Approve Vendor Documentation | GEWIP-030103-050 - Pipes Valves and Fittings - Complete Manufacture and Inspection | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030104-010 - Electrical Equipment - Issue Request for Quotation | GEWIP-030104-020 - Electrical Equipment - Complete Tender Evaluation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030104-020 - Electrical Equipment - Complete Tender Evaluation | GEWIP-030104-030 - Electrical Equipment - Award Purchase Order | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030104-030 - Electrical Equipment - Award Purchase Order | GEWIP-030104-040 - Electrical Equipment - Approve Vendor Documentation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030104-040 - Electrical Equipment - Approve Vendor Documentation | GEWIP-030104-050 - Electrical Equipment - Complete Manufacture and Inspection | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030105-010 - Instruments and SCADA Equipment - Issue Request for Quotation | GEWIP-030105-020 - Instruments and SCADA Equipment - Complete Tender Evaluation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030105-020 - Instruments and SCADA Equipment - Complete Tender Evaluation | GEWIP-030105-030 - Instruments and SCADA Equipment - Award Purchase Order | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030105-030 - Instruments and SCADA Equipment - Award Purchase Order | GEWIP-030105-040 - Instruments and SCADA Equipment - Approve Vendor Documentation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030105-040 - Instruments and SCADA Equipment - Approve Vendor Documentation | GEWIP-030105-050 - Instruments and SCADA Equipment - Complete Manufacture and Inspection | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030106-010 - Structural Steel and Buildings - Issue Request for Quotation | GEWIP-030106-020 - Structural Steel and Buildings - Complete Tender Evaluation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030106-020 - Structural Steel and Buildings - Complete Tender Evaluation | GEWIP-030106-030 - Structural Steel and Buildings - Award Purchase Order | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030106-030 - Structural Steel and Buildings - Award Purchase Order | GEWIP-030106-040 - Structural Steel and Buildings - Approve Vendor Documentation | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030106-040 - Structural Steel and Buildings - Approve Vendor Documentation | GEWIP-030106-050 - Structural Steel and Buildings - Complete Manufacture and Inspection | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-030106-050 - Structural Steel and Buildings - Complete Manufacture and Inspection | GEWIP-030106-060 - Structural Steel and Buildings - Deliver to Site | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-0401-010 - Award Construction Contract | GEWIP-0401-020 - Approve Construction Execution Plan | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-0401-020 - Approve Construction Execution Plan | GEWIP-0401-030 - Mobilise Project Team | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-0401-030 - Mobilise Project Team | GEWIP-0401-040 - Establish Temporary Site Facilities | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-0401-040 - Establish Temporary Site Facilities | GEWIP-0401-050 - Complete Site Inductions and Permits | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-0401-050 - Complete Site Inductions and Permits | GEWIP-0401-060 - Site Ready for Construction Milestone | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-050101-010 - Site Preparation - Release Work Area | GEWIP-050101-020 - Site Preparation - Complete Survey and Set-Out | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-050101-020 - Site Preparation - Complete Survey and Set-Out | GEWIP-050101-030 - Site Preparation - Install Erosion and Sediment Controls | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-050101-030 - Site Preparation - Install Erosion and Sediment Controls | GEWIP-050101-040 - Site Preparation - Clear and Grub | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-050101-040 - Site Preparation - Clear and Grub | GEWIP-050101-050 - Site Preparation - Strip and Stockpile Topsoil | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-050102-010 - Bulk Earthworks - Release Work Area | GEWIP-050102-020 - Bulk Earthworks - Complete Survey and Set-Out | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-050102-020 - Bulk Earthworks - Complete Survey and Set-Out | GEWIP-050102-030 - Bulk Earthworks - Install Erosion and Sediment Controls | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-050102-030 - Bulk Earthworks - Install Erosion and Sediment Controls | GEWIP-050102-040 - Bulk Earthworks - Clear and Grub | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-050102-040 - Bulk Earthworks - Clear and Grub | GEWIP-050102-050 - Bulk Earthworks - Strip and Stockpile Topsoil | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-050102-050 - Bulk Earthworks - Strip and Stockpile Topsoil | GEWIP-050102-060 - Bulk Earthworks - Complete Bulk Earthworks | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-050103-010 - Concrete and Foundations - Release Foundation Area | GEWIP-050103-020 - Concrete and Foundations - Complete Survey and Set-Out | Finish-to-Start | 0.0 | Standard relationship |
| GEWIP-050103-020 - Concrete and Foundations - Complete Survey and Set-Out | GEWIP-050103-030 - Concrete and Foundations - Excavate Foundations | Finish-to-Start | 0.0 | Standard relationship |
Finds activities that are not properly connected to the schedule network and may move without affecting the project finish.
5 discrete activities (1.7%) have missing predecessor or successor logic across the whole schedule, including completed work. Level of Effort and WBS Summary activities are excluded.
4 incomplete discrete activities (2.0%) have missing logic. Level of Effort and WBS Summary activities are excluded from this current-forecast measure.
| Activity ID | Activity Name | Status | Type | Issue |
|---|---|---|---|---|
| GEWIP-01-040 | Practical Completion Milestone | Not Started | Finish Milestone | Missing successor |
| GEWIP-05020201-050 | Clear Water Storage Tank - Install Reinforcement | Not Started | Activity | Missing successor |
| GEWIP-05020204-040 | Chemical Storage Area - Prepare Subgrade | Not Started | Activity | Missing successor |
| GEWIP-05020101-130 | Intake Works - Handover Civil Works | Not Started | Activity | Missing successor |
Shows date controls applied to activities and distinguishes hard constraints from softer planning restrictions.
No date constraints were found on incomplete activities.
Shows where the programme has no contingency, limited flexibility or unusually high float that may signal weak logic.
148 of 196 assessed activities (75.5%) have negative, zero or high float and warrant management review.
| Activity ID | Activity Name | Status | Total Float (Days) | Float Band | Risk |
|---|---|---|---|---|---|
| GEWIP-020206-050 | Vendor Design - Issue for Client Review | In Progress | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-01-030 | Construction Start Milestone | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-01-040 | Practical Completion Milestone | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050101-010 | Site Preparation - Release Work Area | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050101-020 | Site Preparation - Complete Survey and Set-Out | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050101-030 | Site Preparation - Install Erosion and Sediment Controls | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050101-040 | Site Preparation - Clear and Grub | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050101-050 | Site Preparation - Strip and Stockpile Topsoil | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050102-010 | Bulk Earthworks - Release Work Area | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050102-020 | Bulk Earthworks - Complete Survey and Set-Out | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050102-030 | Bulk Earthworks - Install Erosion and Sediment Controls | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050102-040 | Bulk Earthworks - Clear and Grub | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050102-050 | Bulk Earthworks - Strip and Stockpile Topsoil | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050102-060 | Bulk Earthworks - Complete Bulk Earthworks | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-010 | Concrete and Foundations - Release Foundation Area | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-020 | Concrete and Foundations - Complete Survey and Set-Out | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020207-010 | Plant Electrical Works - Approve Electrical Work Pack | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020207-020 | Plant Electrical Works - Receive Electrical Equipment | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020207-030 | Plant Electrical Works - Install Equipment Supports | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020207-040 | Plant Electrical Works - Install Switchboards | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020208-010 | Plant Instrumentation - Approve Control System Work Pack | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020208-020 | Plant Instrumentation - Receive Instruments and Panels | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020208-030 | Plant Instrumentation - Install Control Panels | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020208-040 | Plant Instrumentation - Install Field Instruments | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020208-050 | Plant Instrumentation - Install Instrument Cables | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020209-010 | SCADA and Control System - Approve Control System Work Pack | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020209-020 | SCADA and Control System - Receive Instruments and Panels | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020209-030 | SCADA and Control System - Install Control Panels | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-05020209-040 | SCADA and Control System - Install Field Instruments | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0601-010 | Approve Pre-Commissioning Plan | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0601-020 | Complete System Walkdowns | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0601-030 | Close Construction Punch Items | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0601-040 | Complete Dry Functional Tests | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0601-050 | Ready for Commissioning Milestone | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0602-010 | Introduce Water to System | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0602-020 | Start Process Equipment | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0602-030 | Complete Integrated System Testing | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0602-040 | Complete Performance Test | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0602-050 | Operational Acceptance Milestone | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0603-010 | Submit Operations and Maintenance Manuals | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0603-020 | Complete Operator Training | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0603-030 | Submit As-Built Drawings | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0603-040 | Close Remaining Punch Items | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-0603-050 | Final Handover Milestone | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-030 | Concrete and Foundations - Excavate Foundations | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-040 | Concrete and Foundations - Place Blinding Concrete | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-050 | Concrete and Foundations - Install Below-Ground Services | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-060 | Concrete and Foundations - Install Formwork | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-070 | Concrete and Foundations - Install Reinforcement | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-080 | Concrete and Foundations - Install Embedded Items | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-090 | Concrete and Foundations - Complete Pre-Pour Inspection | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-100 | Concrete and Foundations - Place Concrete | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-110 | Concrete and Foundations - Cure Concrete | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-120 | Concrete and Foundations - Strip Formwork | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-130 | Concrete and Foundations - Complete Concrete Repairs | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-140 | Concrete and Foundations - Apply Protective Coating | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-150 | Concrete and Foundations - Backfill Foundations | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-160 | Concrete and Foundations - Install Equipment Plinths | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-170 | Concrete and Foundations - Grout Baseplates | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-180 | Concrete and Foundations - Complete Dimensional Survey | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-190 | Concrete and Foundations - Complete Quality Records | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-200 | Concrete and Foundations - Handover Foundations | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-050103-210 | Concrete and Foundations - Close Foundation Work Pack | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GEWIP-030104-040 | Electrical Equipment - Approve Vendor Documentation | In Progress | 49.0 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-030104-050 | Electrical Equipment - Complete Manufacture and Inspection | Not Started | 49.0 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05020203-010 | Sludge Handling System - Approve Installation Work Pack | Not Started | 51.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05020203-020 | Sludge Handling System - Receive and Inspect Equipment | Not Started | 51.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05020203-030 | Sludge Handling System - Prepare Foundations | Not Started | 51.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030201-010 | High Voltage Supply - Approve Electrical Work Pack | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030201-020 | High Voltage Supply - Receive Electrical Equipment | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030201-030 | High Voltage Supply - Install Equipment Supports | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030201-040 | High Voltage Supply - Install Switchboards | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030201-050 | High Voltage Supply - Install Cable Trays | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030202-010 | Low Voltage Distribution - Approve Electrical Work Pack | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030202-020 | Low Voltage Distribution - Receive Electrical Equipment | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030202-030 | Low Voltage Distribution - Install Equipment Supports | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030202-040 | Low Voltage Distribution - Install Switchboards | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030204-010 | Communications and Control Network - Approve Control System Work Pack | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030204-020 | Communications and Control Network - Receive Instruments and Panels | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030204-030 | Communications and Control Network - Install Control Panels | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030204-040 | Communications and Control Network - Install Field Instruments | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030204-050 | Communications and Control Network - Install Instrument Cables | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030204-060 | Communications and Control Network - Terminate and Label Cables | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030204-070 | Communications and Control Network - Complete Loop Checks | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030204-080 | Communications and Control Network - Load Control Software | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030204-090 | Communications and Control Network - Complete Functional Testing | Not Started | 61.2 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-030103-040 | Pipes Valves and Fittings - Approve Vendor Documentation | In Progress | 90.0 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-030103-050 | Pipes Valves and Fittings - Complete Manufacture and Inspection | Not Started | 90.0 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-030102-040 | Pumps and Mechanical Equipment - Approve Vendor Documentation | In Progress | 94.0 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-030102-050 | Pumps and Mechanical Equipment - Complete Manufacture and Inspection | Not Started | 94.0 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-030106-040 | Structural Steel and Buildings - Approve Vendor Documentation | In Progress | 102.0 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-030106-050 | Structural Steel and Buildings - Complete Manufacture and Inspection | Not Started | 102.0 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-030106-060 | Structural Steel and Buildings - Deliver to Site | Not Started | 102.0 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-030105-040 | Instruments and SCADA Equipment - Approve Vendor Documentation | In Progress | 103.0 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-030105-050 | Instruments and SCADA Equipment - Complete Manufacture and Inspection | Not Started | 103.0 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030101-010 | Raw Water Pipeline - Complete Survey and Set-Out | Not Started | 112.5 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030101-020 | Raw Water Pipeline - Clear Pipeline Corridor | Not Started | 112.5 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030101-030 | Raw Water Pipeline - Excavate Trench | Not Started | 112.5 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030101-040 | Raw Water Pipeline - Place Pipe Bedding | Not Started | 112.5 | High Float | May indicate weak logic or excessive contingency |
| GEWIP-05030101-050 | Raw Water Pipeline - String Pipe | Not Started | 112.5 | High Float | May indicate weak logic or excessive contingency |
Checks the working weeks, shifts and exceptions that directly affect activity dates and resource demand.
2 calendars were found; 1 use extended or unusual working patterns. 175 incomplete activities use those calendars.
| Calendar | Type | Hours/Day | Hours/Week | Nominal Days/Week | Exceptions | Activities | Finding |
|---|---|---|---|---|---|---|---|
| GEWIP 7-Day Site Calendar (70 h/week) | Global Calendar | 10.0 | 70.0 | 7.0 | 42 | 175 | Extended or unusual working pattern |
| GEWIP 5-Day Office Calendar (40 h/week) | Global Calendar | 8.0 | 40.0 | 5.0 | 0 | 21 | No immediate issue identified |
Provides the detailed, prioritised corrections behind the Executive Summary and Improvement Plan.
Lists the highest-value corrections in priority order so the planning team can improve the next submission.
| Priority | Finding | Evidence | Why It Matters | Recommended Action |
|---|---|---|---|---|
| Critical | Repair critical-path logic gaps | 1 critical activities have missing logic. | The reported critical path may be incomplete or misleading. | Add valid predecessors or successors and recalculate the schedule before accepting the critical path. |
| Critical | Close current forecast logic gaps | 4 incomplete discrete activities have missing predecessors or successors. | Disconnected work can move without correctly affecting the forecast finish. | Assign planning engineers to validate and close each genuine logic gap. |
| High | Review excessive float | 85 activities (43.4%) exceed 44 working days of total float. | Excessive float can indicate weak logic, broad constraints or unrealistic contingency. | Review high-float paths by WBS and confirm that relationships represent the delivery strategy. |
| High | Break down long-duration activities | 6 incomplete activities exceed 44 working days. | Long activities reduce progress visibility and delay early warning of slippage. | Split major work into measurable control activities with clear handoffs and ownership. |
| High | Improve schedule detail | 6 activities are at least 10% of the exported activity date span. | Broad activities can conceal slippage and make progress reporting subjective. | Break down the highest-risk activities into measurable deliverables with clear completion points. |
| Review | Confirm unusual working calendars | 1 calendars use extended or unusual working patterns. | Forecast dates may depend on shifts or workweeks that are not operationally achievable. | Confirm calendar ownership, holidays and roster assumptions with delivery teams. |
Recognises schedule controls that are working well and should be preserved during corrective action.
Assessment limitation: 4 additional DCMA checks require an approved baseline comparison or a native scheduling-engine sensitivity test. Missing data is not treated as a failure.
Open Resource Analytics