Project: GOLDEN EAGLE WATER INFRASTRUCTURE

Schedule Health Assessment

Overall Schedule Health Score

A single, overall assessment of schedule structure, logic, dates, float, constraints, resources and calendars.

90/100
GOOD

Executive Summary

Translates the detailed checks into a concise management view of schedule reliability, exposure and immediate priorities.

6Management Actions
5High-Priority Actions
10Applicable DCMA-Aligned Checks

GOLDEN EAGLE WATER INFRASTRUCTURE is rated Good with a calculated health score of 90, based only on information available in the uploaded schedule. The separate DCMA-aligned review applied 10 single-schedule checks. The schedule is generally well structured, but targeted corrections remain before full reliance on the forecast. The highest priorities are: Repair critical-path logic gaps; Close current forecast logic gaps; Review excessive float.

View Management Actions Analyse Your Schedule Explore Editable Basis of Schedule

Schedule Improvement Plan

Shows where the score was lost, why it matters and the practical corrections that can improve the next schedule submission.

90/100Overall Schedule Health Score
Up to 10Improvement Opportunity
0Priority Areas

Weighted score across the health areas that can be assessed from one uploaded schedule. Missing information is marked Data not available and is excluded; it never creates a failure or score penalty.

Logic & Network23.2/25
Critical Path & Float13.4/20
Dates & Status15.0/15
Duration & Detail15.0/15
Constraints10.0/10
Resources & Calendars13.5/15
Health AreaScore ContributionImprovement OpportunityStatusWhat We FoundHow to Improve
Logic & Network 23.2/25 Up to 1.8 points Healthy 5 whole-schedule and 4 current logic gaps; 0 leads, 1 lags and 0.0% non-FS relationships. Close genuine logic gaps and replace avoidable leads, lags and complex links. View findings
Critical Path & Float 13.4/20 Up to 6.6 points Needs Review 0 negative-float and 85 high-float activities; 2 priority findings on the reported driving path. Resolve driving-path findings and validate high-float work by WBS. View findings
Dates & Status 15.0/15 Up to 0.0 points Healthy 0 invalid-date activities and 0 with actual dates after the data date. Correct status and date integrity issues before relying on the forecast. View findings
Duration & Detail 15.0/15 Up to 0.0 points Healthy 6 long-duration and 6 insufficient-detail activities. Break broad work into measurable activities with clear completion points. View findings
Constraints 10.0/10 Up to 0.0 points Healthy 0 hard, 0 dated soft and 0 ALAP constraint settings. Confirm contractual constraints and remove unnecessary date controls. View findings
Resources & Calendars 13.5/15 Up to 1.5 points Healthy 100.0% resource coverage; 1 unusual calendars, 0 missing and 0 undefined calendar assignments. Complete resource loading and confirm activity calendars and exceptions. View findings

Project Overview

Confirms the schedule identity, reporting cut-off date and the volume of planning data assessed.

Project NameGOLDEN EAGLE WATER INFRASTRUCTURE
Project ID368
SourcePrimavera P6 — Primavera P6 XER (.xer)
Data Date01-Sep-2026 08:00
Activities290
Relationships331
WBS Elements70
Resources18
Resource Assignments315
Quantity Profiles7
Calendars2

Top Issues and Benchmarks

Prioritises the findings that matter most. Each item shows the affected population, the benchmark used and the next practical action.

High Float — High

85 of 196 assessed activities exceed 44 working days of float (43.4%).

A high proportion can indicate weak logic, broad constraints or unrealistic contingency.

Benchmark: Benchmark: no more than 5% of assessed incomplete activities.

Recommended response: Review high-float paths by WBS and confirm the relationships reflect the delivery strategy. View findings

Current Forecast Logic — Moderate

4 incomplete discrete activities have missing logic (2.0%).

Disconnected work can move without correctly affecting the project forecast finish.

Benchmark: Single-schedule benchmark: no more than 5%; management target: zero unexplained open ends.

Recommended response: Add valid predecessors or successors and retain only documented boundary exceptions. View findings

Look-Ahead Delivery Analytics

Shows work due to start or finish soon, highlighting overdue activities and potential delivery blockers.

5612-Week Activities
23Critical Activities
0Potential Blockers
0Overdue Activities

The 12-week outlook contains 56 activities, including 23 critical activities and 0 with potential delivery blockers. 0 incomplete activities have a forecast start or finish before the data date.

Open Look-Ahead

S-Curves & Progress Analytics

Compares earned, actual and forecast labour or cost using data genuinely available in the uploaded schedule.

7,346Earned Labour Hours
7,640Actual Labour Hours
38,434Forecast Labour Hours
0.8%Forecast vs Current Budget

As at 2026-09-01, 7,639.6 actual labour hours and 7,345.7 earned labour hours are reported. Forecast labour hours are 38,433.8, a variance of 0.8% against the current budgeted total.

Open S-Curves

Weekly Manning

Estimates the average workforce required each week from budgeted labour hours and each activity's assigned calendar.

59.8Peak Average Manning
03-Jan-2027Peak Week

Weekly labour demand is calculated from exported labour-resource target hours using each activity's assigned calendar and calendar exceptions.

Open Weekly Manning

Schedule Distribution Analytics

Shows how activity status, float and remaining duration are distributed so unusual concentrations are easy to identify.

79Low-Float Activities
85High-Float Activities
6Long Remaining Durations

79 incomplete activities (40.3% of assessed float values) have 10 working days or less total float. 6 executable activities (3.1% of assessed durations) have more than 44 working days remaining.

Open Histograms

Resource Loading Coverage

Checks whether incomplete delivery activities have resources or roles assigned. It measures coverage, not workforce capacity.

100.0%Coverage
191Resourced Activities
0Unresourced Activities

191 of 191 eligible incomplete activities (100.0%) have a resource or role assignment. 0 activities have no assignment.

Open Resource Analytics to review weekly demand by labour resource using activity-calendar working hours.

Open Resource Analytics

DCMA-Aligned Schedule Quality Checks

Applies the schedule-quality checks that can be assessed from one file. Baseline comparison and native scheduling tests belong in the comparison workflow.

90/100DCMA-Aligned Check Score
10Applicable Checks
9Passed
1Need Correction

10 single-schedule checks were applicable: 9 passed, 0 need review and 1 failed. The remaining 4 checks require an approved baseline comparison, source data that was not exported, or a native scheduling-engine test.

Equal weighting of testable DCMA checks: Pass = 1 point, Review = 0.5 points and Fail = 0 points. Not Tested checks are excluded from the calculated score.

The DCMA-Aligned Check Score uses a separate pass/fail assessment method and may differ from the Overall Schedule Health Score.

CheckResultThresholdStatusBasis
1. Logic 4 (2.0%) <= 5% Pass Incomplete discrete activities missing a predecessor or successor; Level of Effort and WBS Summary activities excluded
2. Leads 0 (0.0%) 0% Pass Relationships with negative lag
3. Lags 1 (0.3%) <= 5% Pass Relationships with positive lag
4. Relationship Types 0 (0.0%) <= 10% non-FS Pass Relationships that are not Finish-to-Start
5. Hard Constraints 0 (0.0%) <= 5% Pass Start On or Finish On constraints
6. High Float 85 (43.4%) <= 5% Fail Incomplete activities with more than 44 working days of float
7. Negative Float 0 (0.0%) 0% Pass Incomplete activities with negative total float
8. High Duration 6 (3.1%) <= 5% Pass Incomplete task or resource-dependent activities longer than 44 working days
9. Invalid Dates 0 0 Pass Inconsistent dates or actual dates after the data date
10. Resources 191 (100.0%) Informational Pass Eligible incomplete activities with resource assignments

Schedule Dates & Duration Analysis

Checks reporting dates and activity durations for conditions that can hide slippage or weaken progress measurement.

Project Start01-Apr-2026
Data Date01-Sep-2026 08:00
Forecast Finish09-Jun-2027
6Long Durations
6Insufficient Detail
0Invalid Dates
0Future Actual Dates

6 activities need date or duration review: 6 exceed 44 working days, 0 have inconsistent values, and 0 contain actual dates after the data date.

6 activities (2.1%) have an original duration of at least 43.4 days, equal to 10% of the 434.0-day activity date span.

Activity IDActivity NameStatusOriginal DurationRemaining DurationStartFinishIssue
GEWIP-030101-050 Treatment Process Equipment - Complete Manufacture and Inspection Not Started 45.0 days 45.0 days 15-Sep-2026 16-Nov-2026 Original duration exceeds 44 working days
GEWIP-030102-050 Pumps and Mechanical Equipment - Complete Manufacture and Inspection Not Started 45.0 days 45.0 days 11-Sep-2026 12-Nov-2026 Original duration exceeds 44 working days
GEWIP-030103-050 Pipes Valves and Fittings - Complete Manufacture and Inspection Not Started 45.0 days 45.0 days 11-Sep-2026 12-Nov-2026 Original duration exceeds 44 working days
GEWIP-030104-050 Electrical Equipment - Complete Manufacture and Inspection Not Started 45.0 days 45.0 days 15-Sep-2026 16-Nov-2026 Original duration exceeds 44 working days
GEWIP-030105-050 Instruments and SCADA Equipment - Complete Manufacture and Inspection Not Started 45.0 days 45.0 days 15-Sep-2026 16-Nov-2026 Original duration exceeds 44 working days
GEWIP-030106-050 Structural Steel and Buildings - Complete Manufacture and Inspection Not Started 45.0 days 45.0 days 15-Sep-2026 16-Nov-2026 Original duration exceeds 44 working days

Longest Path & Driving Path Analysis

Identifies the chain of work most likely to control the forecast finish and the issues that could make that path unreliable.

26Path Activities
210.6Remaining Working Days
5Milestones
2Activities at Risk

26 activities are identified using Primavera driving activity flag, with 210.6 total remaining working days across the listed activities. 2 activities contain logic, constraint, float, resource or date findings.

Method: Primavera driving activity flag

Primavera identified the driving activities but did not export Float Path 1 order. They are displayed chronologically and should not be read as a calculated network sequence.

Missing Logic2
Constrained Activities0
Unresourced Activities0
Negative Float Activities0
OrderActivity IDActivity NameStatusStartFinishRemaining DaysTotal FloatLink from PriorLagRisk
1 GEWIP-030104-040 Electrical Equipment - Approve Vendor Documentation In Progress 25-Aug-2026 14-Sep-2026 9.8 49.0 Path start 0 days No immediate issue identified
2 GEWIP-030106-040 Structural Steel and Buildings - Approve Vendor Documentation In Progress 25-Aug-2026 14-Sep-2026 9.8 102.0 No direct link to prior row 0 days No immediate issue identified
3 GEWIP-020206-050 Vendor Design - Issue for Client Review In Progress 28-Aug-2026 03-Sep-2026 1.9 0.0 No direct link to prior row 0 days No immediate issue identified
4 GEWIP-01-030 Construction Start Milestone Not Started 04-Sep-2026 04-Sep-2026 0.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
5 GEWIP-030104-050 Electrical Equipment - Complete Manufacture and Inspection Not Started 15-Sep-2026 16-Nov-2026 45.0 49.0 No direct link to prior row 0 days No immediate issue identified
6 GEWIP-030106-050 Structural Steel and Buildings - Complete Manufacture and Inspection Not Started 15-Sep-2026 16-Nov-2026 45.0 102.0 No direct link to prior row 0 days No immediate issue identified
7 GEWIP-030106-060 Structural Steel and Buildings - Deliver to Site Not Started 17-Nov-2026 23-Nov-2026 5.0 102.0 Finish-to-Start 0.0 days No immediate issue identified
8 GEWIP-05020101-040 Intake Works - Prepare Subgrade Not Started 01-Jan-2027 03-Jan-2027 3.0 161.2 No direct link to prior row 0 days No immediate issue identified
9 GEWIP-05020101-120 Intake Works - Complete Quality Records Not Started 29-Jan-2027 30-Jan-2027 2.0 161.2 No direct link to prior row 0 days No immediate issue identified
10 GEWIP-05020101-130 Intake Works - Handover Civil Works Not Started 31-Jan-2027 31-Jan-2027 1.0 161.2 Finish-to-Start 0.0 days Missing logic
11 GEWIP-0601-010 Approve Pre-Commissioning Plan Not Started 26-Feb-2027 02-Mar-2027 5.0 0.0 No direct link to prior row 0 days No immediate issue identified
12 GEWIP-0601-020 Complete System Walkdowns Not Started 03-Mar-2027 12-Mar-2027 10.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
13 GEWIP-0601-030 Close Construction Punch Items Not Started 13-Mar-2027 17-Mar-2027 5.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
14 GEWIP-0601-040 Complete Dry Functional Tests Not Started 18-Mar-2027 27-Mar-2027 10.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
15 GEWIP-0601-050 Ready for Commissioning Milestone Not Started 28-Mar-2027 28-Mar-2027 0.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
16 GEWIP-0602-010 Introduce Water to System Not Started 29-Mar-2027 31-Mar-2027 3.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
17 GEWIP-0602-020 Start Process Equipment Not Started 01-Apr-2027 05-Apr-2027 5.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
18 GEWIP-0602-030 Complete Integrated System Testing Not Started 06-Apr-2027 15-Apr-2027 10.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
19 GEWIP-0602-040 Complete Performance Test Not Started 16-Apr-2027 25-Apr-2027 10.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
20 GEWIP-0602-050 Operational Acceptance Milestone Not Started 26-Apr-2027 26-Apr-2027 0.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
21 GEWIP-0603-010 Submit Operations and Maintenance Manuals Not Started 27-Apr-2027 10-May-2027 10.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
22 GEWIP-0603-020 Complete Operator Training Not Started 11-May-2027 17-May-2027 5.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
23 GEWIP-0603-030 Submit As-Built Drawings Not Started 18-May-2027 31-May-2027 10.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
24 GEWIP-0603-040 Close Remaining Punch Items Not Started 01-Jun-2027 07-Jun-2027 5.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
25 GEWIP-0603-050 Final Handover Milestone Not Started 08-Jun-2027 08-Jun-2027 0.0 0.0 Finish-to-Start 0.0 days No immediate issue identified
26 GEWIP-01-040 Practical Completion Milestone Not Started 09-Jun-2027 09-Jun-2027 0.0 0.0 Finish-to-Start 0.0 days Missing logic

Critical Path Analysis

Highlights activities with little or no scheduling flexibility and the milestones most exposed to delay.

63Critical Activities
16Near-Critical Activities
32.1%Critical Percentage
5Critical Milestones

63 incomplete activities (32.1%) are critical and 16 are near-critical with up to 10 working days of float. 1 critical activities have missing logic and 0 are constrained.

Method: Total Float <= 0 hours

Activity IDActivity NameStatusTypeTotal Float (Days)Risk
GEWIP-020206-050 Vendor Design - Issue for Client Review In Progress Activity 0.0 Critical
GEWIP-01-030 Construction Start Milestone Not Started Start Milestone 0.0 Critical
GEWIP-01-040 Practical Completion Milestone Not Started Finish Milestone 0.0 Critical, Missing logic
GEWIP-050101-010 Site Preparation - Release Work Area Not Started Activity 0.0 Critical
GEWIP-050101-020 Site Preparation - Complete Survey and Set-Out Not Started Activity 0.0 Critical
GEWIP-050101-030 Site Preparation - Install Erosion and Sediment Controls Not Started Activity 0.0 Critical
GEWIP-050101-040 Site Preparation - Clear and Grub Not Started Activity 0.0 Critical
GEWIP-050101-050 Site Preparation - Strip and Stockpile Topsoil Not Started Activity 0.0 Critical
GEWIP-050102-010 Bulk Earthworks - Release Work Area Not Started Activity 0.0 Critical
GEWIP-050102-020 Bulk Earthworks - Complete Survey and Set-Out Not Started Activity 0.0 Critical
GEWIP-050102-030 Bulk Earthworks - Install Erosion and Sediment Controls Not Started Activity 0.0 Critical
GEWIP-050102-040 Bulk Earthworks - Clear and Grub Not Started Activity 0.0 Critical
GEWIP-050102-050 Bulk Earthworks - Strip and Stockpile Topsoil Not Started Activity 0.0 Critical
GEWIP-050102-060 Bulk Earthworks - Complete Bulk Earthworks Not Started Activity 0.0 Critical
GEWIP-050103-010 Concrete and Foundations - Release Foundation Area Not Started Activity 0.0 Critical
GEWIP-050103-020 Concrete and Foundations - Complete Survey and Set-Out Not Started Activity 0.0 Critical
GEWIP-05020207-010 Plant Electrical Works - Approve Electrical Work Pack Not Started Activity 0.0 Critical
GEWIP-05020207-020 Plant Electrical Works - Receive Electrical Equipment Not Started Activity 0.0 Critical
GEWIP-05020207-030 Plant Electrical Works - Install Equipment Supports Not Started Activity 0.0 Critical
GEWIP-05020207-040 Plant Electrical Works - Install Switchboards Not Started Activity 0.0 Critical
GEWIP-05020208-010 Plant Instrumentation - Approve Control System Work Pack Not Started Activity 0.0 Critical
GEWIP-05020208-020 Plant Instrumentation - Receive Instruments and Panels Not Started Activity 0.0 Critical
GEWIP-05020208-030 Plant Instrumentation - Install Control Panels Not Started Activity 0.0 Critical
GEWIP-05020208-040 Plant Instrumentation - Install Field Instruments Not Started Activity 0.0 Critical
GEWIP-05020208-050 Plant Instrumentation - Install Instrument Cables Not Started Activity 0.0 Critical
GEWIP-05020209-010 SCADA and Control System - Approve Control System Work Pack Not Started Activity 0.0 Critical
GEWIP-05020209-020 SCADA and Control System - Receive Instruments and Panels Not Started Activity 0.0 Critical
GEWIP-05020209-030 SCADA and Control System - Install Control Panels Not Started Activity 0.0 Critical
GEWIP-05020209-040 SCADA and Control System - Install Field Instruments Not Started Activity 0.0 Critical
GEWIP-0601-010 Approve Pre-Commissioning Plan Not Started Activity 0.0 Critical
GEWIP-0601-020 Complete System Walkdowns Not Started Activity 0.0 Critical
GEWIP-0601-030 Close Construction Punch Items Not Started Activity 0.0 Critical
GEWIP-0601-040 Complete Dry Functional Tests Not Started Activity 0.0 Critical
GEWIP-0601-050 Ready for Commissioning Milestone Not Started Finish Milestone 0.0 Critical
GEWIP-0602-010 Introduce Water to System Not Started Activity 0.0 Critical
GEWIP-0602-020 Start Process Equipment Not Started Activity 0.0 Critical
GEWIP-0602-030 Complete Integrated System Testing Not Started Activity 0.0 Critical
GEWIP-0602-040 Complete Performance Test Not Started Activity 0.0 Critical
GEWIP-0602-050 Operational Acceptance Milestone Not Started Finish Milestone 0.0 Critical
GEWIP-0603-010 Submit Operations and Maintenance Manuals Not Started Activity 0.0 Critical
GEWIP-0603-020 Complete Operator Training Not Started Activity 0.0 Critical
GEWIP-0603-030 Submit As-Built Drawings Not Started Activity 0.0 Critical
GEWIP-0603-040 Close Remaining Punch Items Not Started Activity 0.0 Critical
GEWIP-0603-050 Final Handover Milestone Not Started Finish Milestone 0.0 Critical
GEWIP-050103-030 Concrete and Foundations - Excavate Foundations Not Started Activity 0.0 Critical
GEWIP-050103-040 Concrete and Foundations - Place Blinding Concrete Not Started Activity 0.0 Critical
GEWIP-050103-050 Concrete and Foundations - Install Below-Ground Services Not Started Activity 0.0 Critical
GEWIP-050103-060 Concrete and Foundations - Install Formwork Not Started Activity 0.0 Critical
GEWIP-050103-070 Concrete and Foundations - Install Reinforcement Not Started Activity 0.0 Critical
GEWIP-050103-080 Concrete and Foundations - Install Embedded Items Not Started Activity 0.0 Critical
GEWIP-050103-090 Concrete and Foundations - Complete Pre-Pour Inspection Not Started Activity 0.0 Critical
GEWIP-050103-100 Concrete and Foundations - Place Concrete Not Started Activity 0.0 Critical
GEWIP-050103-110 Concrete and Foundations - Cure Concrete Not Started Activity 0.0 Critical
GEWIP-050103-120 Concrete and Foundations - Strip Formwork Not Started Activity 0.0 Critical
GEWIP-050103-130 Concrete and Foundations - Complete Concrete Repairs Not Started Activity 0.0 Critical
GEWIP-050103-140 Concrete and Foundations - Apply Protective Coating Not Started Activity 0.0 Critical
GEWIP-050103-150 Concrete and Foundations - Backfill Foundations Not Started Activity 0.0 Critical
GEWIP-050103-160 Concrete and Foundations - Install Equipment Plinths Not Started Activity 0.0 Critical
GEWIP-050103-170 Concrete and Foundations - Grout Baseplates Not Started Activity 0.0 Critical
GEWIP-050103-180 Concrete and Foundations - Complete Dimensional Survey Not Started Activity 0.0 Critical
GEWIP-050103-190 Concrete and Foundations - Complete Quality Records Not Started Activity 0.0 Critical
GEWIP-050103-200 Concrete and Foundations - Handover Foundations Not Started Activity 0.0 Critical
GEWIP-050103-210 Concrete and Foundations - Close Foundation Work Pack Not Started Activity 0.0 Critical
GEWIP-05020206-010 Mechanical Equipment - Approve Installation Work Pack Not Started Activity 2.5 Near-critical
GEWIP-05020206-020 Mechanical Equipment - Receive and Inspect Equipment Not Started Activity 2.5 Near-critical
GEWIP-05020206-030 Mechanical Equipment - Prepare Foundations Not Started Activity 2.5 Near-critical
GEWIP-05020206-040 Mechanical Equipment - Install Major Equipment Not Started Activity 2.5 Near-critical
GEWIP-05020202-010 Treated Water Pump Station - Approve Installation Work Pack Not Started Activity 10.0 Near-critical
GEWIP-05020202-020 Treated Water Pump Station - Receive and Inspect Equipment Not Started Activity 10.0 Near-critical
GEWIP-05020202-030 Treated Water Pump Station - Prepare Foundations Not Started Activity 10.0 Near-critical
GEWIP-05020202-040 Treated Water Pump Station - Install Major Equipment Not Started Activity 10.0 Near-critical
GEWIP-05030105-010 Surge Protection System - Complete Survey and Set-Out Not Started Activity 10.0 Near-critical
GEWIP-05030105-020 Surge Protection System - Clear Pipeline Corridor Not Started Activity 10.0 Near-critical
GEWIP-05030105-030 Surge Protection System - Excavate Trench Not Started Activity 10.0 Near-critical
GEWIP-05030105-040 Surge Protection System - Place Pipe Bedding Not Started Activity 10.0 Near-critical
GEWIP-05030106-010 Pipeline Testing and Disinfection - Complete Survey and Set-Out Not Started Activity 10.0 Near-critical
GEWIP-05030106-020 Pipeline Testing and Disinfection - Clear Pipeline Corridor Not Started Activity 10.0 Near-critical
GEWIP-05030106-030 Pipeline Testing and Disinfection - Excavate Trench Not Started Activity 10.0 Near-critical
GEWIP-05030106-040 Pipeline Testing and Disinfection - Place Pipe Bedding Not Started Activity 10.0 Near-critical

Logic & Relationship Analysis

Reviews how activities are connected, including complex links, leads and lags that can make the forecast difficult to trust.

331Relationships
1.14Relationships per Activity
2.28Logic Connections per Activity
0.0%Non-FS Logic
1Leads & Lags
5Merge Hotspots

331 relationships equal 1.14 relationships per activity and 2.28 predecessor/successor connections per activity. 0 (0.0%) are not Finish-to-Start and 1 (0.3%) contain leads or lags. 5 discrete activities have three or more predecessors.

Finish-to-Start331
Start-to-Start0
Finish-to-Finish0
Start-to-Finish0
Activities affected by positive lag1
Activities affected by negative lag0
Highly connected activities (>10 total links)1
PredecessorSuccessorRelationshipLag (Days)Finding
GEWIP-01-010 - Notice to Proceed Milestone GEWIP-01-020 - Baseline Schedule Approved Milestone Finish-to-Start 10.0 Lag delays the linked activity
GEWIP-020101-010 - Preliminary Process Design - Confirm Design Criteria GEWIP-020101-020 - Preliminary Process Design - Complete Design Calculations Finish-to-Start 0.0 Standard relationship
GEWIP-020101-020 - Preliminary Process Design - Complete Design Calculations GEWIP-020101-030 - Preliminary Process Design - Prepare Drawings and Specifications Finish-to-Start 0.0 Standard relationship
GEWIP-020101-030 - Preliminary Process Design - Prepare Drawings and Specifications GEWIP-020101-040 - Preliminary Process Design - Complete Interdisciplinary Review Finish-to-Start 0.0 Standard relationship
GEWIP-020101-040 - Preliminary Process Design - Complete Interdisciplinary Review GEWIP-020101-050 - Preliminary Process Design - Issue for Client Review Finish-to-Start 0.0 Standard relationship
GEWIP-020101-050 - Preliminary Process Design - Issue for Client Review GEWIP-020101-060 - Preliminary Process Design - Incorporate Review Comments Finish-to-Start 0.0 Standard relationship
GEWIP-020101-060 - Preliminary Process Design - Incorporate Review Comments GEWIP-020101-070 - Preliminary Process Design - Issue for Construction Finish-to-Start 0.0 Standard relationship
GEWIP-020102-010 - Preliminary Civil Design - Confirm Design Criteria GEWIP-020102-020 - Preliminary Civil Design - Complete Design Calculations Finish-to-Start 0.0 Standard relationship
GEWIP-020102-020 - Preliminary Civil Design - Complete Design Calculations GEWIP-020102-030 - Preliminary Civil Design - Prepare Drawings and Specifications Finish-to-Start 0.0 Standard relationship
GEWIP-020102-030 - Preliminary Civil Design - Prepare Drawings and Specifications GEWIP-020102-040 - Preliminary Civil Design - Complete Interdisciplinary Review Finish-to-Start 0.0 Standard relationship
GEWIP-020102-040 - Preliminary Civil Design - Complete Interdisciplinary Review GEWIP-020102-050 - Preliminary Civil Design - Issue for Client Review Finish-to-Start 0.0 Standard relationship
GEWIP-020102-050 - Preliminary Civil Design - Issue for Client Review GEWIP-020102-060 - Preliminary Civil Design - Incorporate Review Comments Finish-to-Start 0.0 Standard relationship
GEWIP-020102-060 - Preliminary Civil Design - Incorporate Review Comments GEWIP-020102-070 - Preliminary Civil Design - Issue for Construction Finish-to-Start 0.0 Standard relationship
GEWIP-020103-010 - Preliminary Mechanical Design - Confirm Design Criteria GEWIP-020103-020 - Preliminary Mechanical Design - Complete Design Calculations Finish-to-Start 0.0 Standard relationship
GEWIP-020103-020 - Preliminary Mechanical Design - Complete Design Calculations GEWIP-020103-030 - Preliminary Mechanical Design - Prepare Drawings and Specifications Finish-to-Start 0.0 Standard relationship
GEWIP-020103-030 - Preliminary Mechanical Design - Prepare Drawings and Specifications GEWIP-020103-040 - Preliminary Mechanical Design - Complete Interdisciplinary Review Finish-to-Start 0.0 Standard relationship
GEWIP-020103-040 - Preliminary Mechanical Design - Complete Interdisciplinary Review GEWIP-020103-050 - Preliminary Mechanical Design - Issue for Client Review Finish-to-Start 0.0 Standard relationship
GEWIP-020103-050 - Preliminary Mechanical Design - Issue for Client Review GEWIP-020103-060 - Preliminary Mechanical Design - Incorporate Review Comments Finish-to-Start 0.0 Standard relationship
GEWIP-020104-010 - Preliminary Electrical Design - Confirm Design Criteria GEWIP-020104-020 - Preliminary Electrical Design - Complete Design Calculations Finish-to-Start 0.0 Standard relationship
GEWIP-020104-020 - Preliminary Electrical Design - Complete Design Calculations GEWIP-020104-030 - Preliminary Electrical Design - Prepare Drawings and Specifications Finish-to-Start 0.0 Standard relationship
GEWIP-020104-030 - Preliminary Electrical Design - Prepare Drawings and Specifications GEWIP-020104-040 - Preliminary Electrical Design - Complete Interdisciplinary Review Finish-to-Start 0.0 Standard relationship
GEWIP-020104-040 - Preliminary Electrical Design - Complete Interdisciplinary Review GEWIP-020104-050 - Preliminary Electrical Design - Issue for Client Review Finish-to-Start 0.0 Standard relationship
GEWIP-020104-050 - Preliminary Electrical Design - Issue for Client Review GEWIP-020104-060 - Preliminary Electrical Design - Incorporate Review Comments Finish-to-Start 0.0 Standard relationship
GEWIP-020104-060 - Preliminary Electrical Design - Incorporate Review Comments GEWIP-020104-070 - Preliminary Electrical Design - Issue for Construction Finish-to-Start 0.0 Standard relationship
GEWIP-020105-010 - Environmental Approvals - Confirm Approval Requirements GEWIP-020105-020 - Environmental Approvals - Prepare Environmental Documentation Finish-to-Start 0.0 Standard relationship
GEWIP-020105-020 - Environmental Approvals - Prepare Environmental Documentation GEWIP-020105-030 - Environmental Approvals - Submit Approval Application Finish-to-Start 0.0 Standard relationship
GEWIP-020105-030 - Environmental Approvals - Submit Approval Application GEWIP-020105-040 - Environmental Approvals - Respond to Authority Comments Finish-to-Start 0.0 Standard relationship
GEWIP-020105-040 - Environmental Approvals - Respond to Authority Comments GEWIP-020105-050 - Environmental Approvals - Obtain Environmental Approval Finish-to-Start 0.0 Standard relationship
GEWIP-020105-050 - Environmental Approvals - Obtain Environmental Approval GEWIP-020105-060 - Environmental Approvals - Issue Approval Conditions Finish-to-Start 0.0 Standard relationship
GEWIP-020105-060 - Environmental Approvals - Issue Approval Conditions GEWIP-020105-070 - Environmental Approvals - Close Approval Actions Finish-to-Start 0.0 Standard relationship
GEWIP-020201-010 - Process and Hydraulic Design - Confirm Design Criteria GEWIP-020201-020 - Process and Hydraulic Design - Complete Design Calculations Finish-to-Start 0.0 Standard relationship
GEWIP-020201-020 - Process and Hydraulic Design - Complete Design Calculations GEWIP-020201-030 - Process and Hydraulic Design - Prepare Drawings and Specifications Finish-to-Start 0.0 Standard relationship
GEWIP-020201-030 - Process and Hydraulic Design - Prepare Drawings and Specifications GEWIP-020201-040 - Process and Hydraulic Design - Complete Interdisciplinary Review Finish-to-Start 0.0 Standard relationship
GEWIP-020201-040 - Process and Hydraulic Design - Complete Interdisciplinary Review GEWIP-020201-050 - Process and Hydraulic Design - Issue for Client Review Finish-to-Start 0.0 Standard relationship
GEWIP-020201-050 - Process and Hydraulic Design - Issue for Client Review GEWIP-020201-060 - Process and Hydraulic Design - Incorporate Review Comments Finish-to-Start 0.0 Standard relationship
GEWIP-020202-010 - Civil and Structural Design - Confirm Design Criteria GEWIP-020202-020 - Civil and Structural Design - Complete Design Calculations Finish-to-Start 0.0 Standard relationship
GEWIP-020202-020 - Civil and Structural Design - Complete Design Calculations GEWIP-020202-030 - Civil and Structural Design - Prepare Drawings and Specifications Finish-to-Start 0.0 Standard relationship
GEWIP-020202-030 - Civil and Structural Design - Prepare Drawings and Specifications GEWIP-020202-040 - Civil and Structural Design - Complete Interdisciplinary Review Finish-to-Start 0.0 Standard relationship
GEWIP-020202-040 - Civil and Structural Design - Complete Interdisciplinary Review GEWIP-020202-050 - Civil and Structural Design - Issue for Client Review Finish-to-Start 0.0 Standard relationship
GEWIP-020202-050 - Civil and Structural Design - Issue for Client Review GEWIP-020202-060 - Civil and Structural Design - Incorporate Review Comments Finish-to-Start 0.0 Standard relationship
GEWIP-020203-010 - Mechanical and Piping Design - Confirm Design Criteria GEWIP-020203-020 - Mechanical and Piping Design - Complete Design Calculations Finish-to-Start 0.0 Standard relationship
GEWIP-020203-020 - Mechanical and Piping Design - Complete Design Calculations GEWIP-020203-030 - Mechanical and Piping Design - Prepare Drawings and Specifications Finish-to-Start 0.0 Standard relationship
GEWIP-020203-030 - Mechanical and Piping Design - Prepare Drawings and Specifications GEWIP-020203-040 - Mechanical and Piping Design - Complete Interdisciplinary Review Finish-to-Start 0.0 Standard relationship
GEWIP-020203-040 - Mechanical and Piping Design - Complete Interdisciplinary Review GEWIP-020203-050 - Mechanical and Piping Design - Issue for Client Review Finish-to-Start 0.0 Standard relationship
GEWIP-020203-050 - Mechanical and Piping Design - Issue for Client Review GEWIP-020203-060 - Mechanical and Piping Design - Incorporate Review Comments Finish-to-Start 0.0 Standard relationship
GEWIP-020204-010 - Electrical Design - Confirm Design Criteria GEWIP-020204-020 - Electrical Design - Complete Design Calculations Finish-to-Start 0.0 Standard relationship
GEWIP-020204-020 - Electrical Design - Complete Design Calculations GEWIP-020204-030 - Electrical Design - Prepare Drawings and Specifications Finish-to-Start 0.0 Standard relationship
GEWIP-020204-030 - Electrical Design - Prepare Drawings and Specifications GEWIP-020204-040 - Electrical Design - Complete Interdisciplinary Review Finish-to-Start 0.0 Standard relationship
GEWIP-020204-040 - Electrical Design - Complete Interdisciplinary Review GEWIP-020204-050 - Electrical Design - Issue for Client Review Finish-to-Start 0.0 Standard relationship
GEWIP-020204-050 - Electrical Design - Issue for Client Review GEWIP-020204-060 - Electrical Design - Incorporate Review Comments Finish-to-Start 0.0 Standard relationship
GEWIP-020205-010 - Instrumentation and SCADA Design - Confirm Design Criteria GEWIP-020205-020 - Instrumentation and SCADA Design - Complete Design Calculations Finish-to-Start 0.0 Standard relationship
GEWIP-020205-020 - Instrumentation and SCADA Design - Complete Design Calculations GEWIP-020205-030 - Instrumentation and SCADA Design - Prepare Drawings and Specifications Finish-to-Start 0.0 Standard relationship
GEWIP-020205-030 - Instrumentation and SCADA Design - Prepare Drawings and Specifications GEWIP-020205-040 - Instrumentation and SCADA Design - Complete Interdisciplinary Review Finish-to-Start 0.0 Standard relationship
GEWIP-020205-040 - Instrumentation and SCADA Design - Complete Interdisciplinary Review GEWIP-020205-050 - Instrumentation and SCADA Design - Issue for Client Review Finish-to-Start 0.0 Standard relationship
GEWIP-020205-050 - Instrumentation and SCADA Design - Issue for Client Review GEWIP-020205-060 - Instrumentation and SCADA Design - Incorporate Review Comments Finish-to-Start 0.0 Standard relationship
GEWIP-020206-010 - Vendor Design - Confirm Design Criteria GEWIP-020206-020 - Vendor Design - Complete Design Calculations Finish-to-Start 0.0 Standard relationship
GEWIP-020206-020 - Vendor Design - Complete Design Calculations GEWIP-020206-030 - Vendor Design - Prepare Drawings and Specifications Finish-to-Start 0.0 Standard relationship
GEWIP-020206-030 - Vendor Design - Prepare Drawings and Specifications GEWIP-020206-040 - Vendor Design - Complete Interdisciplinary Review Finish-to-Start 0.0 Standard relationship
GEWIP-020206-040 - Vendor Design - Complete Interdisciplinary Review GEWIP-020206-050 - Vendor Design - Issue for Client Review Finish-to-Start 0.0 Standard relationship
GEWIP-030101-010 - Treatment Process Equipment - Issue Request for Quotation GEWIP-030101-020 - Treatment Process Equipment - Complete Tender Evaluation Finish-to-Start 0.0 Standard relationship
GEWIP-030101-020 - Treatment Process Equipment - Complete Tender Evaluation GEWIP-030101-030 - Treatment Process Equipment - Award Purchase Order Finish-to-Start 0.0 Standard relationship
GEWIP-030101-030 - Treatment Process Equipment - Award Purchase Order GEWIP-030101-040 - Treatment Process Equipment - Approve Vendor Documentation Finish-to-Start 0.0 Standard relationship
GEWIP-030101-040 - Treatment Process Equipment - Approve Vendor Documentation GEWIP-030101-050 - Treatment Process Equipment - Complete Manufacture and Inspection Finish-to-Start 0.0 Standard relationship
GEWIP-030102-010 - Pumps and Mechanical Equipment - Issue Request for Quotation GEWIP-030102-020 - Pumps and Mechanical Equipment - Complete Tender Evaluation Finish-to-Start 0.0 Standard relationship
GEWIP-030102-020 - Pumps and Mechanical Equipment - Complete Tender Evaluation GEWIP-030102-030 - Pumps and Mechanical Equipment - Award Purchase Order Finish-to-Start 0.0 Standard relationship
GEWIP-030102-030 - Pumps and Mechanical Equipment - Award Purchase Order GEWIP-030102-040 - Pumps and Mechanical Equipment - Approve Vendor Documentation Finish-to-Start 0.0 Standard relationship
GEWIP-030102-040 - Pumps and Mechanical Equipment - Approve Vendor Documentation GEWIP-030102-050 - Pumps and Mechanical Equipment - Complete Manufacture and Inspection Finish-to-Start 0.0 Standard relationship
GEWIP-030103-010 - Pipes Valves and Fittings - Issue Request for Quotation GEWIP-030103-020 - Pipes Valves and Fittings - Complete Tender Evaluation Finish-to-Start 0.0 Standard relationship
GEWIP-030103-020 - Pipes Valves and Fittings - Complete Tender Evaluation GEWIP-030103-030 - Pipes Valves and Fittings - Award Purchase Order Finish-to-Start 0.0 Standard relationship
GEWIP-030103-030 - Pipes Valves and Fittings - Award Purchase Order GEWIP-030103-040 - Pipes Valves and Fittings - Approve Vendor Documentation Finish-to-Start 0.0 Standard relationship
GEWIP-030103-040 - Pipes Valves and Fittings - Approve Vendor Documentation GEWIP-030103-050 - Pipes Valves and Fittings - Complete Manufacture and Inspection Finish-to-Start 0.0 Standard relationship
GEWIP-030104-010 - Electrical Equipment - Issue Request for Quotation GEWIP-030104-020 - Electrical Equipment - Complete Tender Evaluation Finish-to-Start 0.0 Standard relationship
GEWIP-030104-020 - Electrical Equipment - Complete Tender Evaluation GEWIP-030104-030 - Electrical Equipment - Award Purchase Order Finish-to-Start 0.0 Standard relationship
GEWIP-030104-030 - Electrical Equipment - Award Purchase Order GEWIP-030104-040 - Electrical Equipment - Approve Vendor Documentation Finish-to-Start 0.0 Standard relationship
GEWIP-030104-040 - Electrical Equipment - Approve Vendor Documentation GEWIP-030104-050 - Electrical Equipment - Complete Manufacture and Inspection Finish-to-Start 0.0 Standard relationship
GEWIP-030105-010 - Instruments and SCADA Equipment - Issue Request for Quotation GEWIP-030105-020 - Instruments and SCADA Equipment - Complete Tender Evaluation Finish-to-Start 0.0 Standard relationship
GEWIP-030105-020 - Instruments and SCADA Equipment - Complete Tender Evaluation GEWIP-030105-030 - Instruments and SCADA Equipment - Award Purchase Order Finish-to-Start 0.0 Standard relationship
GEWIP-030105-030 - Instruments and SCADA Equipment - Award Purchase Order GEWIP-030105-040 - Instruments and SCADA Equipment - Approve Vendor Documentation Finish-to-Start 0.0 Standard relationship
GEWIP-030105-040 - Instruments and SCADA Equipment - Approve Vendor Documentation GEWIP-030105-050 - Instruments and SCADA Equipment - Complete Manufacture and Inspection Finish-to-Start 0.0 Standard relationship
GEWIP-030106-010 - Structural Steel and Buildings - Issue Request for Quotation GEWIP-030106-020 - Structural Steel and Buildings - Complete Tender Evaluation Finish-to-Start 0.0 Standard relationship
GEWIP-030106-020 - Structural Steel and Buildings - Complete Tender Evaluation GEWIP-030106-030 - Structural Steel and Buildings - Award Purchase Order Finish-to-Start 0.0 Standard relationship
GEWIP-030106-030 - Structural Steel and Buildings - Award Purchase Order GEWIP-030106-040 - Structural Steel and Buildings - Approve Vendor Documentation Finish-to-Start 0.0 Standard relationship
GEWIP-030106-040 - Structural Steel and Buildings - Approve Vendor Documentation GEWIP-030106-050 - Structural Steel and Buildings - Complete Manufacture and Inspection Finish-to-Start 0.0 Standard relationship
GEWIP-030106-050 - Structural Steel and Buildings - Complete Manufacture and Inspection GEWIP-030106-060 - Structural Steel and Buildings - Deliver to Site Finish-to-Start 0.0 Standard relationship
GEWIP-0401-010 - Award Construction Contract GEWIP-0401-020 - Approve Construction Execution Plan Finish-to-Start 0.0 Standard relationship
GEWIP-0401-020 - Approve Construction Execution Plan GEWIP-0401-030 - Mobilise Project Team Finish-to-Start 0.0 Standard relationship
GEWIP-0401-030 - Mobilise Project Team GEWIP-0401-040 - Establish Temporary Site Facilities Finish-to-Start 0.0 Standard relationship
GEWIP-0401-040 - Establish Temporary Site Facilities GEWIP-0401-050 - Complete Site Inductions and Permits Finish-to-Start 0.0 Standard relationship
GEWIP-0401-050 - Complete Site Inductions and Permits GEWIP-0401-060 - Site Ready for Construction Milestone Finish-to-Start 0.0 Standard relationship
GEWIP-050101-010 - Site Preparation - Release Work Area GEWIP-050101-020 - Site Preparation - Complete Survey and Set-Out Finish-to-Start 0.0 Standard relationship
GEWIP-050101-020 - Site Preparation - Complete Survey and Set-Out GEWIP-050101-030 - Site Preparation - Install Erosion and Sediment Controls Finish-to-Start 0.0 Standard relationship
GEWIP-050101-030 - Site Preparation - Install Erosion and Sediment Controls GEWIP-050101-040 - Site Preparation - Clear and Grub Finish-to-Start 0.0 Standard relationship
GEWIP-050101-040 - Site Preparation - Clear and Grub GEWIP-050101-050 - Site Preparation - Strip and Stockpile Topsoil Finish-to-Start 0.0 Standard relationship
GEWIP-050102-010 - Bulk Earthworks - Release Work Area GEWIP-050102-020 - Bulk Earthworks - Complete Survey and Set-Out Finish-to-Start 0.0 Standard relationship
GEWIP-050102-020 - Bulk Earthworks - Complete Survey and Set-Out GEWIP-050102-030 - Bulk Earthworks - Install Erosion and Sediment Controls Finish-to-Start 0.0 Standard relationship
GEWIP-050102-030 - Bulk Earthworks - Install Erosion and Sediment Controls GEWIP-050102-040 - Bulk Earthworks - Clear and Grub Finish-to-Start 0.0 Standard relationship
GEWIP-050102-040 - Bulk Earthworks - Clear and Grub GEWIP-050102-050 - Bulk Earthworks - Strip and Stockpile Topsoil Finish-to-Start 0.0 Standard relationship
GEWIP-050102-050 - Bulk Earthworks - Strip and Stockpile Topsoil GEWIP-050102-060 - Bulk Earthworks - Complete Bulk Earthworks Finish-to-Start 0.0 Standard relationship
GEWIP-050103-010 - Concrete and Foundations - Release Foundation Area GEWIP-050103-020 - Concrete and Foundations - Complete Survey and Set-Out Finish-to-Start 0.0 Standard relationship
GEWIP-050103-020 - Concrete and Foundations - Complete Survey and Set-Out GEWIP-050103-030 - Concrete and Foundations - Excavate Foundations Finish-to-Start 0.0 Standard relationship

Logic Gap Analysis

Finds activities that are not properly connected to the schedule network and may move without affecting the project finish.

5Whole Schedule Gaps
4Current Forecast Gaps
0Current Missing Predecessors
4Current Missing Successors

5 discrete activities (1.7%) have missing predecessor or successor logic across the whole schedule, including completed work. Level of Effort and WBS Summary activities are excluded.

4 incomplete discrete activities (2.0%) have missing logic. Level of Effort and WBS Summary activities are excluded from this current-forecast measure.

Activity IDActivity NameStatusTypeIssue
GEWIP-01-040 Practical Completion Milestone Not Started Finish Milestone Missing successor
GEWIP-05020201-050 Clear Water Storage Tank - Install Reinforcement Not Started Activity Missing successor
GEWIP-05020204-040 Chemical Storage Area - Prepare Subgrade Not Started Activity Missing successor
GEWIP-05020101-130 Intake Works - Handover Civil Works Not Started Activity Missing successor

Constraints Analysis

Shows date controls applied to activities and distinguishes hard constraints from softer planning restrictions.

0Activities Affected
0Hard Constraints
0Dated Soft Constraints
0As Late As Possible

No date constraints were found on incomplete activities.

Float Analysis

Shows where the programme has no contingency, limited flexibility or unusually high float that may signal weak logic.

0Negative Float
63Zero Float
16Low Float
32Normal Float
85High Float

148 of 196 assessed activities (75.5%) have negative, zero or high float and warrant management review.

Activity IDActivity NameStatusTotal Float (Days)Float BandRisk
GEWIP-020206-050 Vendor Design - Issue for Client Review In Progress 0.0 Zero Float No available schedule contingency
GEWIP-01-030 Construction Start Milestone Not Started 0.0 Zero Float No available schedule contingency
GEWIP-01-040 Practical Completion Milestone Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050101-010 Site Preparation - Release Work Area Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050101-020 Site Preparation - Complete Survey and Set-Out Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050101-030 Site Preparation - Install Erosion and Sediment Controls Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050101-040 Site Preparation - Clear and Grub Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050101-050 Site Preparation - Strip and Stockpile Topsoil Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050102-010 Bulk Earthworks - Release Work Area Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050102-020 Bulk Earthworks - Complete Survey and Set-Out Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050102-030 Bulk Earthworks - Install Erosion and Sediment Controls Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050102-040 Bulk Earthworks - Clear and Grub Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050102-050 Bulk Earthworks - Strip and Stockpile Topsoil Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050102-060 Bulk Earthworks - Complete Bulk Earthworks Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-010 Concrete and Foundations - Release Foundation Area Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-020 Concrete and Foundations - Complete Survey and Set-Out Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020207-010 Plant Electrical Works - Approve Electrical Work Pack Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020207-020 Plant Electrical Works - Receive Electrical Equipment Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020207-030 Plant Electrical Works - Install Equipment Supports Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020207-040 Plant Electrical Works - Install Switchboards Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020208-010 Plant Instrumentation - Approve Control System Work Pack Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020208-020 Plant Instrumentation - Receive Instruments and Panels Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020208-030 Plant Instrumentation - Install Control Panels Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020208-040 Plant Instrumentation - Install Field Instruments Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020208-050 Plant Instrumentation - Install Instrument Cables Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020209-010 SCADA and Control System - Approve Control System Work Pack Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020209-020 SCADA and Control System - Receive Instruments and Panels Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020209-030 SCADA and Control System - Install Control Panels Not Started 0.0 Zero Float No available schedule contingency
GEWIP-05020209-040 SCADA and Control System - Install Field Instruments Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0601-010 Approve Pre-Commissioning Plan Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0601-020 Complete System Walkdowns Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0601-030 Close Construction Punch Items Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0601-040 Complete Dry Functional Tests Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0601-050 Ready for Commissioning Milestone Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0602-010 Introduce Water to System Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0602-020 Start Process Equipment Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0602-030 Complete Integrated System Testing Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0602-040 Complete Performance Test Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0602-050 Operational Acceptance Milestone Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0603-010 Submit Operations and Maintenance Manuals Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0603-020 Complete Operator Training Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0603-030 Submit As-Built Drawings Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0603-040 Close Remaining Punch Items Not Started 0.0 Zero Float No available schedule contingency
GEWIP-0603-050 Final Handover Milestone Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-030 Concrete and Foundations - Excavate Foundations Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-040 Concrete and Foundations - Place Blinding Concrete Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-050 Concrete and Foundations - Install Below-Ground Services Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-060 Concrete and Foundations - Install Formwork Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-070 Concrete and Foundations - Install Reinforcement Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-080 Concrete and Foundations - Install Embedded Items Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-090 Concrete and Foundations - Complete Pre-Pour Inspection Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-100 Concrete and Foundations - Place Concrete Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-110 Concrete and Foundations - Cure Concrete Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-120 Concrete and Foundations - Strip Formwork Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-130 Concrete and Foundations - Complete Concrete Repairs Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-140 Concrete and Foundations - Apply Protective Coating Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-150 Concrete and Foundations - Backfill Foundations Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-160 Concrete and Foundations - Install Equipment Plinths Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-170 Concrete and Foundations - Grout Baseplates Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-180 Concrete and Foundations - Complete Dimensional Survey Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-190 Concrete and Foundations - Complete Quality Records Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-200 Concrete and Foundations - Handover Foundations Not Started 0.0 Zero Float No available schedule contingency
GEWIP-050103-210 Concrete and Foundations - Close Foundation Work Pack Not Started 0.0 Zero Float No available schedule contingency
GEWIP-030104-040 Electrical Equipment - Approve Vendor Documentation In Progress 49.0 High Float May indicate weak logic or excessive contingency
GEWIP-030104-050 Electrical Equipment - Complete Manufacture and Inspection Not Started 49.0 High Float May indicate weak logic or excessive contingency
GEWIP-05020203-010 Sludge Handling System - Approve Installation Work Pack Not Started 51.2 High Float May indicate weak logic or excessive contingency
GEWIP-05020203-020 Sludge Handling System - Receive and Inspect Equipment Not Started 51.2 High Float May indicate weak logic or excessive contingency
GEWIP-05020203-030 Sludge Handling System - Prepare Foundations Not Started 51.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030201-010 High Voltage Supply - Approve Electrical Work Pack Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030201-020 High Voltage Supply - Receive Electrical Equipment Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030201-030 High Voltage Supply - Install Equipment Supports Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030201-040 High Voltage Supply - Install Switchboards Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030201-050 High Voltage Supply - Install Cable Trays Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030202-010 Low Voltage Distribution - Approve Electrical Work Pack Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030202-020 Low Voltage Distribution - Receive Electrical Equipment Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030202-030 Low Voltage Distribution - Install Equipment Supports Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030202-040 Low Voltage Distribution - Install Switchboards Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030204-010 Communications and Control Network - Approve Control System Work Pack Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030204-020 Communications and Control Network - Receive Instruments and Panels Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030204-030 Communications and Control Network - Install Control Panels Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030204-040 Communications and Control Network - Install Field Instruments Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030204-050 Communications and Control Network - Install Instrument Cables Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030204-060 Communications and Control Network - Terminate and Label Cables Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030204-070 Communications and Control Network - Complete Loop Checks Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030204-080 Communications and Control Network - Load Control Software Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-05030204-090 Communications and Control Network - Complete Functional Testing Not Started 61.2 High Float May indicate weak logic or excessive contingency
GEWIP-030103-040 Pipes Valves and Fittings - Approve Vendor Documentation In Progress 90.0 High Float May indicate weak logic or excessive contingency
GEWIP-030103-050 Pipes Valves and Fittings - Complete Manufacture and Inspection Not Started 90.0 High Float May indicate weak logic or excessive contingency
GEWIP-030102-040 Pumps and Mechanical Equipment - Approve Vendor Documentation In Progress 94.0 High Float May indicate weak logic or excessive contingency
GEWIP-030102-050 Pumps and Mechanical Equipment - Complete Manufacture and Inspection Not Started 94.0 High Float May indicate weak logic or excessive contingency
GEWIP-030106-040 Structural Steel and Buildings - Approve Vendor Documentation In Progress 102.0 High Float May indicate weak logic or excessive contingency
GEWIP-030106-050 Structural Steel and Buildings - Complete Manufacture and Inspection Not Started 102.0 High Float May indicate weak logic or excessive contingency
GEWIP-030106-060 Structural Steel and Buildings - Deliver to Site Not Started 102.0 High Float May indicate weak logic or excessive contingency
GEWIP-030105-040 Instruments and SCADA Equipment - Approve Vendor Documentation In Progress 103.0 High Float May indicate weak logic or excessive contingency
GEWIP-030105-050 Instruments and SCADA Equipment - Complete Manufacture and Inspection Not Started 103.0 High Float May indicate weak logic or excessive contingency
GEWIP-05030101-010 Raw Water Pipeline - Complete Survey and Set-Out Not Started 112.5 High Float May indicate weak logic or excessive contingency
GEWIP-05030101-020 Raw Water Pipeline - Clear Pipeline Corridor Not Started 112.5 High Float May indicate weak logic or excessive contingency
GEWIP-05030101-030 Raw Water Pipeline - Excavate Trench Not Started 112.5 High Float May indicate weak logic or excessive contingency
GEWIP-05030101-040 Raw Water Pipeline - Place Pipe Bedding Not Started 112.5 High Float May indicate weak logic or excessive contingency
GEWIP-05030101-050 Raw Water Pipeline - String Pipe Not Started 112.5 High Float May indicate weak logic or excessive contingency

Calendar Analysis

Checks the working weeks, shifts and exceptions that directly affect activity dates and resource demand.

2Calendars
1Unusual Patterns
175Activities Affected
0Unused Calendars

2 calendars were found; 1 use extended or unusual working patterns. 175 incomplete activities use those calendars.

CalendarTypeHours/DayHours/WeekNominal Days/WeekExceptionsActivitiesFinding
GEWIP 7-Day Site Calendar (70 h/week) Global Calendar 10.0 70.0 7.0 42 175 Extended or unusual working pattern
GEWIP 5-Day Office Calendar (40 h/week) Global Calendar 8.0 40.0 5.0 0 21 No immediate issue identified

Management Action Plan

Provides the detailed, prioritised corrections behind the Executive Summary and Improvement Plan.

Recommended Management Actions

Lists the highest-value corrections in priority order so the planning team can improve the next submission.

PriorityFindingEvidenceWhy It MattersRecommended Action
Critical Repair critical-path logic gaps 1 critical activities have missing logic. The reported critical path may be incomplete or misleading. Add valid predecessors or successors and recalculate the schedule before accepting the critical path.
Critical Close current forecast logic gaps 4 incomplete discrete activities have missing predecessors or successors. Disconnected work can move without correctly affecting the forecast finish. Assign planning engineers to validate and close each genuine logic gap.
High Review excessive float 85 activities (43.4%) exceed 44 working days of total float. Excessive float can indicate weak logic, broad constraints or unrealistic contingency. Review high-float paths by WBS and confirm that relationships represent the delivery strategy.
High Break down long-duration activities 6 incomplete activities exceed 44 working days. Long activities reduce progress visibility and delay early warning of slippage. Split major work into measurable control activities with clear handoffs and ownership.
High Improve schedule detail 6 activities are at least 10% of the exported activity date span. Broad activities can conceal slippage and make progress reporting subjective. Break down the highest-risk activities into measurable deliverables with clear completion points.
Review Confirm unusual working calendars 1 calendars use extended or unusual working patterns. Forecast dates may depend on shifts or workweeks that are not operationally achievable. Confirm calendar ownership, holidays and roster assumptions with delivery teams.

Positive Controls

Recognises schedule controls that are working well and should be preserved during corrective action.

Assessment limitation: 4 additional DCMA checks require an approved baseline comparison or a native scheduling-engine sensitivity test. Missing data is not treated as a failure.

Open Resource Analytics