A single, overall assessment of schedule structure, logic, dates, float, constraints, resources and calendars.
Translates the detailed checks into a concise management view of schedule reliability, exposure and immediate priorities.
GOLDEN EAGLE WATER INFRASTRUCTURE is rated Needs Review with a calculated health score of 66, based only on information available in the uploaded schedule. The separate DCMA-aligned review applied 10 single-schedule checks. The schedule requires corrective action before it should be relied on as the primary control forecast. The highest priorities are: Resolve negative float; Repair critical-path logic gaps; Close current forecast logic gaps.
View Management Actions Analyse Your Schedule Explore Editable Basis of ScheduleShows where the score was lost, why it matters and the practical corrections that can improve the next schedule submission.
Weighted score across the health areas that can be assessed from one uploaded schedule. Missing information is marked Data not available and is excluded; it never creates a failure or score penalty.
| Health Area | Score Contribution | Improvement Opportunity | Status | What We Found | How to Improve |
|---|---|---|---|---|---|
| Logic & Network | 17.0/25 | Up to 8.0 points | Needs Review | 2 whole-schedule and 1 current logic gaps; 0 leads, 0 lags and 0.0% non-FS relationships. | Close genuine logic gaps and replace avoidable leads, lags and complex links. View findings |
| Critical Path & Float | 10.0/20 | Up to 10.0 points | Priority | 2 negative-float and 0 high-float activities; 3 priority findings on the reported driving path. | Resolve driving-path findings and validate high-float work by WBS. View findings |
| Dates & Status | 15.0/15 | Up to 0.0 points | Healthy | 0 invalid-date activities and 0 with actual dates after the data date. | Correct status and date integrity issues before relying on the forecast. View findings |
| Duration & Detail | 0/15 | Up to 15 points | Priority | 3 long-duration and 4 insufficient-detail activities. | Break broad work into measurable activities with clear completion points. View findings |
| Constraints | 10.0/10 | Up to 0.0 points | Healthy | 0 hard, 0 dated soft and 0 ALAP constraint settings. | Confirm contractual constraints and remove unnecessary date controls. View findings |
| Resources & Calendars | 13.5/15 | Up to 1.5 points | Healthy | 100.0% resource coverage; 2 unusual calendars, 0 missing and 0 undefined calendar assignments. | Complete resource loading and confirm activity calendars and exceptions. View findings |
Confirms the schedule identity, reporting cut-off date and the volume of planning data assessed.
| Project Name | GOLDEN EAGLE WATER INFRASTRUCTURE |
| Project ID | 900001 |
| Source | Primavera P6 — Primavera P6 XER (.xer) |
| Data Date | 14-Jul-2026 06:00 |
| Activities | 8 |
| Relationships | 7 |
| Resources | 7 |
| Calendars | 4 |
Prioritises the findings that matter most. Each item shows the affected population, the benchmark used and the next practical action.
1 incomplete discrete activities have missing logic (16.7%).
Disconnected work can move without correctly affecting the project forecast finish.
Benchmark: Single-schedule benchmark: no more than 5%; management target: zero unexplained open ends.
Recommended response: Add valid predecessors or successors and retain only documented boundary exceptions. View findings
3 incomplete activities exceed 44 working days (60.0%).
Long activities reduce progress visibility and delay early warning of slippage.
Benchmark: Benchmark: no more than 5% of eligible incomplete activities.
Recommended response: Break broad work into measurable control activities with clear completion points. View findings
Shows work due to start or finish soon, highlighting overdue activities and potential delivery blockers.
The 12-week outlook contains 4 activities, including 2 critical activities and 0 with potential delivery blockers. 0 incomplete activities have a forecast start or finish before the data date.
Open Look-AheadCompares earned, actual and forecast labour or cost using data genuinely available in the uploaded schedule.
As at 2026-07-14, 1,960.0 actual labour hours and 1,800.0 earned labour hours are reported. Forecast labour hours are 24,780.0, a variance of 6.8% against the current budgeted total.
Open S-CurvesEstimates the average workforce required each week from budgeted labour hours and each activity's assigned calendar.
Weekly labour demand is calculated from exported labour-resource target hours using each activity's assigned calendar and calendar exceptions.
Open Weekly ManningShows how activity status, float and remaining duration are distributed so unusual concentrations are easy to identify.
5 incomplete activities (83.3% of assessed float values) have 10 working days or less total float. 3 executable activities (60.0% of assessed durations) have more than 44 working days remaining.
Open HistogramsChecks whether incomplete delivery activities have resources or roles assigned. It measures coverage, not workforce capacity.
5 of 5 eligible incomplete activities (100.0%) have a resource or role assignment. 0 activities have no assignment.
Open Resource Analytics to review weekly demand by labour resource using activity-calendar working hours.
Open Resource AnalyticsApplies the schedule-quality checks that can be assessed from one file. Baseline comparison and native scheduling tests belong in the comparison workflow.
10 single-schedule checks were applicable: 7 passed, 0 need review and 3 failed. The remaining 4 checks require an approved baseline comparison, source data that was not exported, or a native scheduling-engine test.
Equal weighting of testable DCMA checks: Pass = 1 point, Review = 0.5 points and Fail = 0 points. Not Tested checks are excluded from the calculated score.
The DCMA-Aligned Check Score uses a separate pass/fail assessment method and may differ from the Overall Schedule Health Score.
| Check | Result | Threshold | Status | Basis |
|---|---|---|---|---|
| 1. Logic | 1 (16.7%) | <= 5% | Fail | Incomplete discrete activities missing a predecessor or successor; Level of Effort and WBS Summary activities excluded |
| 2. Leads | 0 (0.0%) | 0% | Pass | Relationships with negative lag |
| 3. Lags | 0 (0.0%) | <= 5% | Pass | Relationships with positive lag |
| 4. Relationship Types | 0 (0.0%) | <= 10% non-FS | Pass | Relationships that are not Finish-to-Start |
| 5. Hard Constraints | 0 (0.0%) | <= 5% | Pass | Start On or Finish On constraints |
| 6. High Float | 0 (0.0%) | <= 5% | Pass | Incomplete activities with more than 44 working days of float |
| 7. Negative Float | 2 (33.3%) | 0% | Fail | Incomplete activities with negative total float |
| 8. High Duration | 3 (60.0%) | <= 5% | Fail | Incomplete task or resource-dependent activities longer than 44 working days |
| 9. Invalid Dates | 0 | 0 | Pass | Inconsistent dates or actual dates after the data date |
| 10. Resources | 5 (100.0%) | Informational | Pass | Eligible incomplete activities with resource assignments |
Checks reporting dates and activity durations for conditions that can hide slippage or weaken progress measurement.
| Project Start | 12-Jan-2026 |
| Data Date | 14-Jul-2026 06:00 |
| Forecast Finish | 27-Aug-2027 |
3 activities need date or duration review: 3 exceed 44 working days, 0 have inconsistent values, and 0 contain actual dates after the data date.
4 activities (66.7%) have an original duration of at least 59.2 days, equal to 10% of the 592.5-day activity date span.
| Activity ID | Activity Name | Status | Original Duration | Remaining Duration | Start | Finish | Issue |
|---|---|---|---|---|---|---|---|
| GE-1500 | Pump station construction | Not Started | 144.0 days | 144.0 days | Not found | Not found | Original duration exceeds 44 working days |
| GE-1400 | Pipeline installation | Not Started | 120.0 days | 120.0 days | Not found | Not found | Original duration exceeds 44 working days |
| GE-1300 | Trunk main earthworks | Not Started | 96.0 days | 96.0 days | Not found | Not found | Original duration exceeds 44 working days |
Identifies the chain of work most likely to control the forecast finish and the issues that could make that path unreliable.
4 activities are identified using Lowest-float critical activity fallback, with 144.0 total remaining working days across the listed activities. 3 activities contain logic, constraint, float, resource or date findings.
Method: Lowest-float critical activity fallback
No Primavera float-path or driving-path designation was exported. Critical activities are shown chronologically; this is not a calculated longest-path sequence.
| Missing Logic | 1 |
| Constrained Activities | 0 |
| Unresourced Activities | 0 |
| Negative Float Activities | 2 |
| Order | Activity ID | Activity Name | Status | Start | Finish | Remaining Days | Total Float | Link from Prior | Lag | Risk |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | GE-1200 | Site establishment | In Progress | 15-Jul-2026 | 28-Jul-2026 | 8.0 | -5.0 | Path start | 0 days | Negative float |
| 2 | GE-1300 | Trunk main earthworks | Not Started | 29-Jul-2026 | 29-Jan-2027 | 96.0 | -3.0 | Finish-to-Start | 0.0 days | Negative float |
| 3 | GE-1600 | Testing and commissioning | Not Started | 31-May-2027 | 20-Aug-2027 | 40.0 | 0.0 | No direct link to prior row | 0 days | No immediate issue identified |
| 4 | GE-9000 | Practical completion | Not Started | 27-Aug-2027 | 27-Aug-2027 | 0.0 | 0.0 | Finish-to-Start | 0.0 days | Missing logic |
Highlights activities with little or no scheduling flexibility and the milestones most exposed to delay.
4 incomplete activities (66.7%) are critical and 1 are near-critical with up to 10 working days of float. 1 critical activities have missing logic and 0 are constrained.
Method: Total Float <= 0 hours
| Activity ID | Activity Name | Status | Type | Total Float (Days) | Risk |
|---|---|---|---|---|---|
| GE-1200 | Site establishment | In Progress | Resource Dependent Activity | -5.0 | Critical |
| GE-1300 | Trunk main earthworks | Not Started | Resource Dependent Activity | -3.0 | Critical |
| GE-1600 | Testing and commissioning | Not Started | Activity | 0.0 | Critical |
| GE-9000 | Practical completion | Not Started | Start Milestone | 0.0 | Critical, Missing logic |
| GE-1400 | Pipeline installation | Not Started | Resource Dependent Activity | 1.0 | Near-critical |
Reviews how activities are connected, including complex links, leads and lags that can make the forecast difficult to trust.
7 relationships equal 0.88 relationships per activity and 1.75 predecessor/successor connections per activity. 0 (0.0%) are not Finish-to-Start and 0 (0.0%) contain leads or lags. 0 discrete activities have three or more predecessors.
| Finish-to-Start | 7 |
| Start-to-Start | 0 |
| Finish-to-Finish | 0 |
| Start-to-Finish | 0 |
| Activities affected by positive lag | 0 |
| Activities affected by negative lag | 0 |
| Highly connected activities (>10 total links) | 0 |
| Predecessor | Successor | Relationship | Lag (Days) | Finding |
|---|---|---|---|---|
| GE-1000 - Notice to Proceed | GE-1100 - Detailed design and approvals | Finish-to-Start | 0.0 | Standard relationship |
| GE-1100 - Detailed design and approvals | GE-1200 - Site establishment | Finish-to-Start | 0.0 | Standard relationship |
| GE-1200 - Site establishment | GE-1300 - Trunk main earthworks | Finish-to-Start | 0.0 | Standard relationship |
| GE-1300 - Trunk main earthworks | GE-1400 - Pipeline installation | Finish-to-Start | 0.0 | Standard relationship |
| GE-1400 - Pipeline installation | GE-1500 - Pump station construction | Finish-to-Start | 0.0 | Standard relationship |
| GE-1500 - Pump station construction | GE-1600 - Testing and commissioning | Finish-to-Start | 0.0 | Standard relationship |
| GE-1600 - Testing and commissioning | GE-9000 - Practical completion | Finish-to-Start | 0.0 | Standard relationship |
Finds activities that are not properly connected to the schedule network and may move without affecting the project finish.
2 discrete activities (25.0%) have missing predecessor or successor logic across the whole schedule, including completed work. Level of Effort and WBS Summary activities are excluded.
1 incomplete discrete activities (16.7%) have missing logic. Level of Effort and WBS Summary activities are excluded from this current-forecast measure.
| Activity ID | Activity Name | Status | Type | Issue |
|---|---|---|---|---|
| GE-9000 | Practical completion | Not Started | Start Milestone | Missing successor |
Shows date controls applied to activities and distinguishes hard constraints from softer planning restrictions.
No date constraints were found on incomplete activities.
Shows where the programme has no contingency, limited flexibility or unusually high float that may signal weak logic.
4 of 6 assessed activities (66.7%) have negative, zero or high float and warrant management review.
| Activity ID | Activity Name | Status | Total Float (Days) | Float Band | Risk |
|---|---|---|---|---|---|
| GE-1200 | Site establishment | In Progress | -5.0 | Negative Float | Forecast dates are under pressure |
| GE-1300 | Trunk main earthworks | Not Started | -3.0 | Negative Float | Forecast dates are under pressure |
| GE-1600 | Testing and commissioning | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GE-9000 | Practical completion | Not Started | 0.0 | Zero Float | No available schedule contingency |
| GE-1400 | Pipeline installation | Not Started | 1.0 | Low Float | Limited schedule contingency |
| GE-1500 | Pump station construction | Not Started | 15.0 | Normal Float | Float is within the review range |
Checks the working weeks, shifts and exceptions that directly affect activity dates and resource demand.
4 calendars were found; 2 use extended or unusual working patterns. 5 incomplete activities use those calendars.
| Calendar | Type | Hours/Day | Hours/Week | Nominal Days/Week | Exceptions | Activities | Finding |
|---|---|---|---|---|---|---|---|
| Golden Eagle 6-Day Construction Calendar | Calendar | 10.0 | 60.0 | 6.0 | 0 | 4 | Extended or unusual working pattern |
| Golden Eagle 7-Day Commissioning Calendar | Calendar | 12.0 | 84.0 | 7.0 | 0 | 1 | Extended or unusual working pattern |
| Golden Eagle 5-Day Office Calendar | Calendar | 8.0 | 40.0 | 5.0 | 0 | 1 | No immediate issue identified |
| Golden Eagle 5-Day Vendor Calendar | Calendar | 9.0 | 45.0 | 5.0 | 0 | 0 | Unused by incomplete activities |
Provides the detailed, prioritised corrections behind the Executive Summary and Improvement Plan.
Lists the highest-value corrections in priority order so the planning team can improve the next submission.
| Priority | Finding | Evidence | Why It Matters | Recommended Action |
|---|---|---|---|---|
| Critical | Resolve negative float | 2 incomplete activities have negative total float. | Contractual or management dates may not be achievable under the current plan. | Review the driving paths, imposed dates and recovery options, then agree accountable actions. |
| Critical | Repair critical-path logic gaps | 1 critical activities have missing logic. | The reported critical path may be incomplete or misleading. | Add valid predecessors or successors and recalculate the schedule before accepting the critical path. |
| Critical | Close current forecast logic gaps | 1 incomplete discrete activities have missing predecessors or successors. | Disconnected work can move without correctly affecting the forecast finish. | Assign planning engineers to validate and close each genuine logic gap. |
| High | Break down long-duration activities | 3 incomplete activities exceed 44 working days. | Long activities reduce progress visibility and delay early warning of slippage. | Split major work into measurable control activities with clear handoffs and ownership. |
| High | Improve schedule detail | 4 activities are at least 10% of the exported activity date span. | Broad activities can conceal slippage and make progress reporting subjective. | Break down the highest-risk activities into measurable deliverables with clear completion points. |
| Review | Confirm unusual working calendars | 2 calendars use extended or unusual working patterns. | Forecast dates may depend on shifts or workweeks that are not operationally achievable. | Confirm calendar ownership, holidays and roster assumptions with delivery teams. |
Recognises schedule controls that are working well and should be preserved during corrective action.
Assessment limitation: 4 additional DCMA checks require an approved baseline comparison or a native scheduling-engine sensitivity test. Missing data is not treated as a failure.