Schedule Distribution Analytics
Turns schedule data into simple distributions so unusual concentrations of status, float or duration are easy to see.
79 incomplete activities (40.3% of assessed float values) have 10 working days or less total float. 6 executable activities (3.1% of assessed durations) have more than 44 working days remaining.
Activities
290
Low-Float Activities
79
High-Float Activities
85
Long Remaining Durations
6
Activity status includes all exported activities. Total float uses incomplete activities and the same 8-hour working-day convention as the Schedule Health Check. Remaining duration includes incomplete task and resource-dependent activities, uses each activity calendar's hours per day, and excludes milestones, level-of-effort and WBS summary activities.
Management Signals
Highlights the distributions that deserve management attention and explains why they matter.
Low-float concentration
79 incomplete activities have 10 working days or less total float.
79 incomplete activities have 10 working days or less total float.
High-float exposure
85 incomplete activities exceed 44 working days of total float.
85 incomplete activities exceed 44 working days of total float.
Long remaining durations
6 executable activities exceed 44 working days remaining duration.
6 executable activities exceed 44 working days remaining duration.
Activity Status Distribution
Shows how the schedule is divided between completed, in-progress and not-started activities.
Total Float Distribution
Shows the scheduling flexibility available on incomplete activities. Low float includes negative, zero and 1-10 working days.
Remaining Duration Distribution
Shows whether remaining work is broken into manageable activities or concentrated in long-duration blocks.