Schedule Distribution Analytics

Turns schedule data into simple distributions so unusual concentrations of status, float or duration are easy to see.

79 incomplete activities (40.3% of assessed float values) have 10 working days or less total float. 6 executable activities (3.1% of assessed durations) have more than 44 working days remaining.

Activities

290

Low-Float Activities

79

High-Float Activities

85

Long Remaining Durations

6

Activity status includes all exported activities. Total float uses incomplete activities and the same 8-hour working-day convention as the Schedule Health Check. Remaining duration includes incomplete task and resource-dependent activities, uses each activity calendar's hours per day, and excludes milestones, level-of-effort and WBS summary activities.

Management Signals

Highlights the distributions that deserve management attention and explains why they matter.

Low-float concentration
79 incomplete activities have 10 working days or less total float.
High-float exposure
85 incomplete activities exceed 44 working days of total float.
Long remaining durations
6 executable activities exceed 44 working days remaining duration.

Activity Status Distribution

Shows how the schedule is divided between completed, in-progress and not-started activities.

Total Float Distribution

Shows the scheduling flexibility available on incomplete activities. Low float includes negative, zero and 1-10 working days.

Remaining Duration Distribution

Shows whether remaining work is broken into manageable activities or concentrated in long-duration blocks.